Golf Terrace Residences By Asak construction progress

The registered completion date for Golf Terrace Residences By Asak is October 2027. At the last site inspection, in May 2026, it was 5.1% built. The developer is Asak Real Estate Development.

5.1%

Built, at the site inspection of 7 May 2026

Running behind its date

Registered completion date
October 2027
Finish at recent pace
April 2033
Construction started
January 2026
First registered
December 2025
Developer
Asak Real Estate Development
Units
105
Escrow bank
Commercial Bank of Dubai
Name in Arabic
غولف تيراس ريزيدنسز من اساك
Project number
4304
Site inspections
2

Schedule

Between December 2025 and May 2026 the site added about 1.1 points a month. At that rate it would finish around April 2033, more than three months after its registered date of October 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

7 May 2026

5.1%+5.1 pts

  • Golf Terrace Residences By Asak construction site, inspection photo 1, 7 May 2026
  • Golf Terrace Residences By Asak construction site, inspection photo 2, 7 May 2026
  • Golf Terrace Residences By Asak construction site, inspection photo 3, 7 May 2026
  • Golf Terrace Residences By Asak construction site, inspection photo 4, 7 May 2026

22 December 2025

0%

  • Golf Terrace Residences By Asak construction site, inspection photo 1, 22 December 2025
  • Golf Terrace Residences By Asak construction site, inspection photo 2, 22 December 2025
  • Golf Terrace Residences By Asak construction site, inspection photo 3, 22 December 2025

All 8 site photos, by inspection date

Context

Own a unit in Golf Terrace Residences By Asak?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Golf Terrace Residences By Asak handover date?
The registered completion date is October 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2033. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Golf Terrace Residences By Asak?
Golf Terrace Residences By Asak was 5.1% built at the site inspection on 7 May 2026. The site has been inspected 2 times since December 2025. The Land Department took 8 site photos at its inspections.
Is Golf Terrace Residences By Asak delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2027.
Who is building Golf Terrace Residences By Asak?
The registered developer is Asak Real Estate Development.
Which bank holds the escrow account for Golf Terrace Residences By Asak?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.