77 Boulevard By Bam construction progress
77 Boulevard By Bam in Jumeirah Village Circle was registered to complete in September 2026 and is still under construction. At the last site inspection, in March 2026, it was 18% built. The developer is Bam Real Estate Development.
18%
Built, at the site inspection of 24 March 2026
3 months past its registered completion date
- Registered completion date
- September 2026
- Finish at recent pace
- September 2031
- Construction started
- January 2025
- First registered
- March 2025
- Developer
- Bam Real Estate Development
- Community
- Jumeirah Village Circle
- Units
- 58
- Escrow bank
- United Bank Limited
- Name in Arabic
- 77 بوليفارد بواسطة بام
- Project number
- 3359
- Site inspections
- 2
Schedule
77 Boulevard By Bam was registered to complete in September 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 1.2 points a month. Kept at that rate, the site would reach 100% around September 2031.
Site inspections
24 March 2026
18%+18 pts
9 January 2025
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Own a unit in 77 Boulevard By Bam?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the 77 Boulevard By Bam handover date?
- The registered completion date was September 2026, and the register still lists 77 Boulevard By Bam as under construction. At the pace of its recent inspections the site would reach 100% around September 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on 77 Boulevard By Bam?
- 77 Boulevard By Bam was 18% built at the site inspection on 24 March 2026. The site has been inspected 2 times since January 2025. The Land Department took 8 site photos at its inspections.
- Is 77 Boulevard By Bam delayed?
- Yes. Its registered completion date of September 2026 has passed and the project is still listed as under construction.
- Who is building 77 Boulevard By Bam?
- The registered developer is Bam Real Estate Development.
- Which bank holds the escrow account for 77 Boulevard By Bam?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.