105 Residences By Kamdar construction progress
The registered completion date for 105 Residences By Kamdar in Jumeirah Village Circle is February 2027. At the last site inspection, in October 2026, it was 12% built. The developer is Kamdar Property Development.
12%
Built, at the site inspection of 15 October 2026
Running behind its date
- Registered completion date
- February 2027
- Finish at recent pace
- August 2033
- Construction started
- March 2025
- First registered
- October 2024
- Developer
- Kamdar Property Development
- Community
- Jumeirah Village Circle
- Units
- 105
- Escrow bank
- Mashreq Bank
- Name in Arabic
- 105 ريزيدنسز من كامدار
- Project number
- 3310
- Site inspections
- 6
Schedule
Between December 2025 and October 2026 the site added about 1.1 points a month. At that rate it would finish around August 2033, more than three months after its registered date of February 2027.
Site inspections
15 October 2026
12%+2.3 pts
13 July 2026
10%+6.5 pts
2 April 2026
3.6%+2.0 pts
11 December 2025
1.6%+1.3 pts
11 July 2025
0.3%+0.3 pts
1 October 2024
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Own a unit in 105 Residences By Kamdar?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the 105 Residences By Kamdar handover date?
- The registered completion date is February 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2033. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on 105 Residences By Kamdar?
- 105 Residences By Kamdar was 12% built at the site inspection on 15 October 2026. The site has been inspected 6 times since October 2024. The Land Department took 23 site photos at its inspections.
- Is 105 Residences By Kamdar delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2027.
- Who is building 105 Residences By Kamdar?
- The registered developer is Kamdar Property Development.
- Which bank holds the escrow account for 105 Residences By Kamdar?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.