105 Residences By Kamdar construction progress
105 Residences By Kamdar in Jumeirah Village Circle is 10% built at the Land Department inspection of July 2026. Developer Kamdar Property Development. Completion registered for February 2027.
10%
Built, at the Land Department site inspection of 13 July 2026
Running behind its date
- Completion date (Land Department)
- February 2027
- Finish at recent pace
- September 2032
- Construction started
- March 2025
- Registered with the Land Department
- October 2024
- Developer
- Kamdar Property Development
- Community
- Jumeirah Village Circle
- Units
- 105
- Escrow bank
- Mashreq Bank
- Name in Arabic
- 105 ريزيدنسز من كامدار
- Land Department project number
- 3310
- Land Department site inspections
- 5
Schedule
Between December 2025 and July 2026 the site added about 1.2 points a month. At that rate it would finish around September 2032, more than three months after the February 2027 date registered with the Land Department.
Site inspections
13 July 2026
10%+6.5 pts
2 April 2026
3.6%+2.0 pts
11 December 2025
1.6%+1.3 pts
11 July 2025
0.3%+0.3 pts
1 October 2024
0%
Context
Jumeirah Village Circle has 119 projects under construction, 40% built on average.
Own a unit in 105 Residences By Kamdar?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will 105 Residences By Kamdar be completed?
- The completion date registered with the Dubai Land Department is February 2027. At the pace of its recent inspections the site would reach 100% around September 2032. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of 105 Residences By Kamdar is built?
- 10%, measured at the Land Department site inspection on 13 July 2026. The Land Department engineers have inspected the site 5 times since October 2024.
- Is 105 Residences By Kamdar delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2027.
- Who is building 105 Residences By Kamdar?
- The registered developer is Kamdar Property Development.
- Which bank holds the escrow account for 105 Residences By Kamdar?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 42%, Due January 2013, passed.
- Serenity Lakes 2Nearby in Jumeirah Village Circle. 50%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 90%, Due April 2026, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.





