D Villas construction progress

The registered completion date for D Villas in Jumeirah Golf Estates is December 2028. At the last site inspection, in September 2026, it was 9.1% built. The developer is Dar Dg Global Properties.

9.1%

Built, at the site inspection of 10 September 2026

Running behind its date

Registered completion date
December 2028
Finish at recent pace
June 2036
Construction started
July 2025
First registered
March 2025
Developer
Dar Dg Global Properties
Units
198
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
دي فيلاز
Project number
3593
Site inspections
4

Schedule

Between November 2025 and September 2026 the site added about 0.8 points a month. At that rate it would finish around June 2036, more than three months after its registered date of December 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

10 September 2026

9.1%+2.5 pts

  • D Villas construction site, inspection photo 1, 10 September 2026
  • D Villas construction site, inspection photo 2, 10 September 2026
  • D Villas construction site, inspection photo 3, 10 September 2026
  • D Villas construction site, inspection photo 4, 10 September 2026

24 April 2026

6.6%+4.9 pts

  • D Villas construction site, inspection photo 1, 24 April 2026
  • D Villas construction site, inspection photo 2, 24 April 2026
  • D Villas construction site, inspection photo 3, 24 April 2026
  • D Villas construction site, inspection photo 4, 24 April 2026

24 November 2025

1.7%+1.7 pts

  • D Villas construction site, inspection photo 1, 24 November 2025
  • D Villas construction site, inspection photo 2, 24 November 2025
  • D Villas construction site, inspection photo 3, 24 November 2025
  • D Villas construction site, inspection photo 4, 24 November 2025

5 March 2025

0%

  • D Villas construction site, inspection photo 1, 5 March 2025
  • D Villas construction site, inspection photo 2, 5 March 2025

All 21 site photos, by inspection date

Context

Jumeirah Golf Estates has 4 projects under construction, 49% built on average.

Own a unit in D Villas?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the D Villas handover date?
The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2036. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on D Villas?
D Villas was 9.1% built at the site inspection on 10 September 2026. The site has been inspected 4 times since March 2025. The Land Department took 21 site photos at its inspections.
Is D Villas delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building D Villas?
The registered developer is Dar Dg Global Properties.
Which bank holds the escrow account for D Villas?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.