D Villas construction progress
The registered completion date for D Villas in Jumeirah Golf Estates is December 2028. At the last site inspection, in September 2026, it was 9.1% built. The developer is Dar Dg Global Properties.
9.1%
Built, at the site inspection of 10 September 2026
Running behind its date
- Registered completion date
- December 2028
- Finish at recent pace
- June 2036
- Construction started
- July 2025
- First registered
- March 2025
- Developer
- Dar Dg Global Properties
- Community
- Jumeirah Golf Estates
- Units
- 198
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- دي فيلاز
- Project number
- 3593
- Site inspections
- 4
Schedule
Between November 2025 and September 2026 the site added about 0.8 points a month. At that rate it would finish around June 2036, more than three months after its registered date of December 2028.
Site inspections
10 September 2026
9.1%+2.5 pts
24 April 2026
6.6%+4.9 pts
24 November 2025
1.7%+1.7 pts
5 March 2025
0%
Context
Jumeirah Golf Estates has 4 projects under construction, 49% built on average.
Own a unit in D Villas?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the D Villas handover date?
- The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2036. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on D Villas?
- D Villas was 9.1% built at the site inspection on 10 September 2026. The site has been inspected 4 times since March 2025. The Land Department took 21 site photos at its inspections.
- Is D Villas delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
- Who is building D Villas?
- The registered developer is Dar Dg Global Properties.
- Which bank holds the escrow account for D Villas?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Jouri HillsNearby in Jumeirah Golf Estates. 78%, Due June 2026, passed.
- Signature MansionsNearby in Jumeirah Golf Estates. 87%, Due May 2026, passed.
- Terra Golf CollectionNearby in Jumeirah Golf Estates. 20%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)