Signature Mansions construction progress

Signature Mansions in Jumeirah Golf Estates is 87% built at the Land Department inspection of June 2026. Developer Signature Jge Real Estate Development. Completion registered for May 2026.

87%

Built, at the Land Department site inspection of 29 June 2026

5 months past its registered completion date

Completion date (Land Department)
May 2026
Finish at recent pace
October 2026
Construction started
January 2023
Registered with the Land Department
February 2023
Developer
Signature Jge Real Estate Development
Units
18
Escrow bank
The National Bank of Fujairah
Name in Arabic
سيجنتشر مانشينز
Land Department project number
2542
Land Department site inspections
11

Schedule

Signature Mansions was registered to complete in May 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 3.8 points a month. Kept at that rate, the site would reach 100% around October 2026.

0%25%50%75%100%202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

29 June 2026

87%+9.4 pts

  • Signature Mansions construction site, Land Department inspection photo 1, 29 June 2026
  • Signature Mansions construction site, Land Department inspection photo 2, 29 June 2026
  • Signature Mansions construction site, Land Department inspection photo 3, 29 June 2026
  • Signature Mansions construction site, Land Department inspection photo 4, 29 June 2026

6 February 2026

78%+24 pts

  • Signature Mansions construction site, Land Department inspection photo 1, 6 February 2026
  • Signature Mansions construction site, Land Department inspection photo 2, 6 February 2026
  • Signature Mansions construction site, Land Department inspection photo 3, 6 February 2026
  • Signature Mansions construction site, Land Department inspection photo 4, 6 February 2026

1 October 2025

53%+9.3 pts

  • Signature Mansions construction site, Land Department inspection photo 1, 1 October 2025
  • Signature Mansions construction site, Land Department inspection photo 2, 1 October 2025
  • Signature Mansions construction site, Land Department inspection photo 3, 1 October 2025
  • Signature Mansions construction site, Land Department inspection photo 4, 1 October 2025

4 June 2025

44%+10 pts

  • Signature Mansions construction site, Land Department inspection photo 1, 4 June 2025
  • Signature Mansions construction site, Land Department inspection photo 2, 4 June 2025
  • Signature Mansions construction site, Land Department inspection photo 3, 4 June 2025
  • Signature Mansions construction site, Land Department inspection photo 4, 4 June 2025

13 March 2025

34%+14 pts

  • Signature Mansions construction site, Land Department inspection photo 1, 13 March 2025
  • Signature Mansions construction site, Land Department inspection photo 2, 13 March 2025
  • Signature Mansions construction site, Land Department inspection photo 3, 13 March 2025
  • Signature Mansions construction site, Land Department inspection photo 4, 13 March 2025

10 October 2024

20%+9.9 pts

  • Signature Mansions construction site, Land Department inspection photo 1, 10 October 2024
  • Signature Mansions construction site, Land Department inspection photo 2, 10 October 2024
  • Signature Mansions construction site, Land Department inspection photo 3, 10 October 2024
  • Signature Mansions construction site, Land Department inspection photo 4, 10 October 2024

20 May 2024

10%+5.5 pts

  • Signature Mansions construction site, Land Department inspection photo 1, 20 May 2024
  • Signature Mansions construction site, Land Department inspection photo 2, 20 May 2024
  • Signature Mansions construction site, Land Department inspection photo 3, 20 May 2024
  • Signature Mansions construction site, Land Department inspection photo 4, 20 May 2024

7 December 2023

4.6%+0.2 pts

  • Signature Mansions construction site, Land Department inspection photo 1, 7 December 2023
  • Signature Mansions construction site, Land Department inspection photo 2, 7 December 2023
  • Signature Mansions construction site, Land Department inspection photo 3, 7 December 2023
  • Signature Mansions construction site, Land Department inspection photo 4, 7 December 2023

22 August 2023

4.4%+1.8 pts

  • Signature Mansions construction site, Land Department inspection photo 1, 22 August 2023
  • Signature Mansions construction site, Land Department inspection photo 2, 22 August 2023
  • Signature Mansions construction site, Land Department inspection photo 3, 22 August 2023
  • Signature Mansions construction site, Land Department inspection photo 4, 22 August 2023

18 May 2023

2.6%+2.6 pts

  • Signature Mansions construction site, Land Department inspection photo 1, 18 May 2023
  • Signature Mansions construction site, Land Department inspection photo 2, 18 May 2023
  • Signature Mansions construction site, Land Department inspection photo 3, 18 May 2023
  • Signature Mansions construction site, Land Department inspection photo 4, 18 May 2023

All 85 site photos, by inspection date

Context

Jumeirah Golf Estates has 4 projects under construction, 49% built on average.

Own a unit in Signature Mansions?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Signature Mansions be completed?
The completion date registered with the Dubai Land Department is May 2026. At the pace of its recent inspections the site would reach 100% around October 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Signature Mansions is built?
87%, measured at the Land Department site inspection on 29 June 2026. The Land Department engineers have inspected the site 11 times since January 2023.
Is Signature Mansions delayed?
Yes. Its registered completion date of May 2026 has passed and the Land Department still lists it as under construction.
Who is building Signature Mansions?
The registered developer is Signature Jge Real Estate Development.
Which bank holds the escrow account for Signature Mansions?
The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.