Rose Gardens 1 construction progress

Rose Gardens 1 in Jumeirah Garden City is 43% built at the Land Department inspection of September 2026. Developer Cavara Real Estate Development. Completion registered for July 2026.

43%

Built, at the Land Department site inspection of 24 September 2026

3 months past its registered completion date

Completion date (Land Department)
July 2026
Finish at recent pace
April 2028
Construction started
January 2025
Registered with the Land Department
April 2025
Units
166
Escrow bank
Emirates NBD
Name in Arabic
روز جاردنز 1
Land Department project number
3506
Land Department site inspections
6

Schedule

Rose Gardens 1 was registered to complete in July 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 3.0 points a month. Kept at that rate, the site would reach 100% around April 2028.

0%25%50%75%100%2026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

24 September 2026

43%+15 pts

  • Rose Gardens 1 construction site, Land Department inspection photo 1, 24 September 2026
  • Rose Gardens 1 construction site, Land Department inspection photo 2, 24 September 2026
  • Rose Gardens 1 construction site, Land Department inspection photo 3, 24 September 2026
  • Rose Gardens 1 construction site, Land Department inspection photo 4, 24 September 2026

8 June 2026

28%+11 pts

  • Rose Gardens 1 construction site, Land Department inspection photo 1, 8 June 2026
  • Rose Gardens 1 construction site, Land Department inspection photo 2, 8 June 2026
  • Rose Gardens 1 construction site, Land Department inspection photo 3, 8 June 2026
  • Rose Gardens 1 construction site, Land Department inspection photo 4, 8 June 2026

18 March 2026

17%+4.5 pts

  • Rose Gardens 1 construction site, Land Department inspection photo 1, 18 March 2026
  • Rose Gardens 1 construction site, Land Department inspection photo 2, 18 March 2026
  • Rose Gardens 1 construction site, Land Department inspection photo 3, 18 March 2026
  • Rose Gardens 1 construction site, Land Department inspection photo 4, 18 March 2026

19 November 2025

13%+11 pts

  • Rose Gardens 1 construction site, Land Department inspection photo 1, 19 November 2025
  • Rose Gardens 1 construction site, Land Department inspection photo 2, 19 November 2025
  • Rose Gardens 1 construction site, Land Department inspection photo 3, 19 November 2025
  • Rose Gardens 1 construction site, Land Department inspection photo 4, 19 November 2025

10 July 2025

2.1%+2.1 pts

  • Rose Gardens 1 construction site, Land Department inspection photo 1, 10 July 2025
  • Rose Gardens 1 construction site, Land Department inspection photo 2, 10 July 2025
  • Rose Gardens 1 construction site, Land Department inspection photo 3, 10 July 2025
  • Rose Gardens 1 construction site, Land Department inspection photo 4, 10 July 2025

15 January 2025

0%

  • Rose Gardens 1 construction site, Land Department inspection photo 1, 15 January 2025
  • Rose Gardens 1 construction site, Land Department inspection photo 2, 15 January 2025

All 35 site photos, by inspection date

Context

Jumeirah Garden City has 27 projects under construction, 30% built on average.

Cavara Real Estate Development has 3 projects under construction in Dubai; 3 have passed their registered completion date.

Own a unit in Rose Gardens 1?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Rose Gardens 1 be completed?
The completion date registered with the Dubai Land Department is July 2026. At the pace of its recent inspections the site would reach 100% around April 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Rose Gardens 1 is built?
43%, measured at the Land Department site inspection on 24 September 2026. The Land Department engineers have inspected the site 6 times since January 2025.
Is Rose Gardens 1 delayed?
Yes. Its registered completion date of July 2026 has passed and the Land Department still lists it as under construction.
Who is building Rose Gardens 1?
The registered developer is Cavara Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Rose Gardens 1?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.