Rose Gardens 3 construction progress

Rose Gardens 3 in Arjan is 76% built at the Land Department inspection of June 2026. Developer Cavara Real Estate Development. Completion registered for May 2026.

76%

Built, at the Land Department site inspection of 5 June 2026

5 months past its registered completion date

Completion date (Land Department)
May 2026
Finish at recent pace
November 2026
Construction started
September 2024
Registered with the Land Department
April 2025
Community
Arjan
Units
49
Escrow bank
Emirates NBD
Name in Arabic
روز جاردنز 3
Land Department project number
3588
Land Department site inspections
5

Schedule

Rose Gardens 3 was registered to complete in May 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 4.8 points a month. Kept at that rate, the site would reach 100% around November 2026.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

5 June 2026

76%+13 pts

  • Rose Gardens 3 construction site, Land Department inspection photo 1, 5 June 2026
  • Rose Gardens 3 construction site, Land Department inspection photo 2, 5 June 2026
  • Rose Gardens 3 construction site, Land Department inspection photo 3, 5 June 2026
  • Rose Gardens 3 construction site, Land Department inspection photo 4, 5 June 2026

23 March 2026

63%+15 pts

  • Rose Gardens 3 construction site, Land Department inspection photo 1, 23 March 2026
  • Rose Gardens 3 construction site, Land Department inspection photo 2, 23 March 2026
  • Rose Gardens 3 construction site, Land Department inspection photo 3, 23 March 2026
  • Rose Gardens 3 construction site, Land Department inspection photo 4, 23 March 2026

4 December 2025

47%+16 pts

  • Rose Gardens 3 construction site, Land Department inspection photo 1, 4 December 2025
  • Rose Gardens 3 construction site, Land Department inspection photo 2, 4 December 2025
  • Rose Gardens 3 construction site, Land Department inspection photo 3, 4 December 2025
  • Rose Gardens 3 construction site, Land Department inspection photo 4, 4 December 2025

28 August 2025

31%+28 pts

  • Rose Gardens 3 construction site, Land Department inspection photo 1, 28 August 2025
  • Rose Gardens 3 construction site, Land Department inspection photo 2, 28 August 2025
  • Rose Gardens 3 construction site, Land Department inspection photo 3, 28 August 2025
  • Rose Gardens 3 construction site, Land Department inspection photo 4, 28 August 2025

28 February 2025

3.0%

  • Rose Gardens 3 construction site, Land Department inspection photo 1, 28 February 2025
  • Rose Gardens 3 construction site, Land Department inspection photo 2, 28 February 2025
  • Rose Gardens 3 construction site, Land Department inspection photo 3, 28 February 2025
  • Rose Gardens 3 construction site, Land Department inspection photo 4, 28 February 2025

All 36 site photos, by inspection date

Context

Arjan has 23 projects under construction, 46% built on average.

Cavara Real Estate Development has 3 projects under construction in Dubai; 3 have passed their registered completion date.

Own a unit in Rose Gardens 3?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Rose Gardens 3 be completed?
The completion date registered with the Dubai Land Department is May 2026. At the pace of its recent inspections the site would reach 100% around November 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Rose Gardens 3 is built?
76%, measured at the Land Department site inspection on 5 June 2026. The Land Department engineers have inspected the site 5 times since February 2025.
Is Rose Gardens 3 delayed?
Yes. Its registered completion date of May 2026 has passed and the Land Department still lists it as under construction.
Who is building Rose Gardens 3?
The registered developer is Cavara Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Rose Gardens 3?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.