81 photos from 12 site inspections, newest first. The percentage is how much of Bulgari Lighthouse Dubai was built on the day of each visit.

8 October 202680% built

9 July 202664% built

15 April 202653% built

15 January 202644% built

15 October 202536% built

25 July 202523% built

30 April 202519% built

16 January 202515% built

20 September 20248.6% built

1 April 20241.4% built

4 September 20230.1% built

10 November 20220% built

Back to Bulgari Lighthouse Dubai construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.