Skip to content

Taiyo Residences construction progress

The registered completion date for Taiyo Residences in Wasl Gate is December 2027. At the last site inspection, in October 2026, it was 12% built. The developer is Continental Investments Lmd.

12%

Built, at the site inspection of 20 October 2026

Running behind its date

Registered completion date
December 2027
Finish at recent pace
June 2034
Construction started
May 2025
First registered
June 2025
Community
Wasl Gate
Units
379
Escrow bank
The National Bank of Fujairah
Name in Arabic
تايو ريزيدنسيز
Project number
3757
Site inspections
5

Schedule

Between November 2025 and October 2026 the site added about 1.0 points a month. At that rate it would finish around June 2034, more than three months after its registered date of December 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

20 October 2026

12%+7.0 pts

  • Taiyo Residences construction site, inspection photo 1, 20 October 2026
  • Taiyo Residences construction site, inspection photo 2, 20 October 2026
  • Taiyo Residences construction site, inspection photo 3, 20 October 2026
  • Taiyo Residences construction site, inspection photo 4, 20 October 2026

13 July 2026

5.1%+1.8 pts

  • Taiyo Residences construction site, inspection photo 1, 13 July 2026
  • Taiyo Residences construction site, inspection photo 2, 13 July 2026
  • Taiyo Residences construction site, inspection photo 3, 13 July 2026
  • Taiyo Residences construction site, inspection photo 4, 13 July 2026

2 March 2026

3.3%+2.0 pts

  • Taiyo Residences construction site, inspection photo 1, 2 March 2026
  • Taiyo Residences construction site, inspection photo 2, 2 March 2026
  • Taiyo Residences construction site, inspection photo 3, 2 March 2026
  • Taiyo Residences construction site, inspection photo 4, 2 March 2026

11 November 2025

1.3%+1.3 pts

  • Taiyo Residences construction site, inspection photo 1, 11 November 2025
  • Taiyo Residences construction site, inspection photo 2, 11 November 2025
  • Taiyo Residences construction site, inspection photo 3, 11 November 2025
  • Taiyo Residences construction site, inspection photo 4, 11 November 2025

14 May 2025

0%

  • Taiyo Residences construction site, inspection photo 1, 14 May 2025
  • Taiyo Residences construction site, inspection photo 2, 14 May 2025

All 21 site photos, by inspection date

Context

Wasl Gate has 13 projects under construction, 21% built on average.

Continental Investments Lmd has 4 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Taiyo Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Taiyo Residences handover date?
The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around June 2034. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Taiyo Residences?
Taiyo Residences was 12% built at the site inspection on 20 October 2026. The site has been inspected 5 times since May 2025. The Land Department took 21 site photos at its inspections.
Is Taiyo Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Taiyo Residences?
The registered developer is Continental Investments Lmd. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Taiyo Residences?
The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.