La Boutique construction photos

30 photos taken by Dubai Land Department engineers at 5 site inspections, newest first. The percentage is how much of La Boutique was built on the day of each visit.

18 June 202638% built

25 March 202622% built

25 November 202514% built

16 July 20254.3% built

19 June 20240% built

Back to La Boutique construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.