The Pier construction progress

The registered completion date for The Pier in Dubai Maritime City is December 2026. At the last site inspection, in October 2026, it was 48% built. The developer is Continental Investments Lmd.

48%

Built, at the site inspection of 20 October 2026

Running behind its date

Registered completion date
December 2026
Finish at recent pace
May 2028
Construction started
July 2024
First registered
July 2024
Units
282
Escrow bank
The National Bank of Fujairah
Name in Arabic
ذا بير
Project number
3110
Site inspections
7

Schedule

Between December 2025 and October 2026 the site added about 2.8 points a month. At that rate it would finish around May 2028, more than three months after its registered date of December 2026.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

20 October 2026

48%+14 pts

  • The Pier construction site, inspection photo 1, 20 October 2026
  • The Pier construction site, inspection photo 2, 20 October 2026
  • The Pier construction site, inspection photo 3, 20 October 2026
  • The Pier construction site, inspection photo 4, 20 October 2026

14 July 2026

35%+8.6 pts

  • The Pier construction site, inspection photo 1, 14 July 2026
  • The Pier construction site, inspection photo 2, 14 July 2026
  • The Pier construction site, inspection photo 3, 14 July 2026
  • The Pier construction site, inspection photo 4, 14 July 2026

10 April 2026

26%+6.3 pts

  • The Pier construction site, inspection photo 1, 10 April 2026
  • The Pier construction site, inspection photo 2, 10 April 2026
  • The Pier construction site, inspection photo 3, 10 April 2026
  • The Pier construction site, inspection photo 4, 10 April 2026

15 December 2025

20%+8.0 pts

  • The Pier construction site, inspection photo 1, 15 December 2025
  • The Pier construction site, inspection photo 2, 15 December 2025
  • The Pier construction site, inspection photo 3, 15 December 2025
  • The Pier construction site, inspection photo 4, 15 December 2025

26 August 2025

12%+6.6 pts

  • The Pier construction site, inspection photo 1, 26 August 2025
  • The Pier construction site, inspection photo 2, 26 August 2025
  • The Pier construction site, inspection photo 3, 26 August 2025
  • The Pier construction site, inspection photo 4, 26 August 2025

2 April 2025

5.4%+5.4 pts

  • The Pier construction site, inspection photo 1, 2 April 2025
  • The Pier construction site, inspection photo 2, 2 April 2025
  • The Pier construction site, inspection photo 3, 2 April 2025

27 June 2024

0%

  • The Pier construction site, inspection photo 1, 27 June 2024

All 46 site photos, by inspection date

Context

Dubai Maritime City has 23 projects under construction, 32% built on average.

Continental Investments Lmd has 4 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Pier?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Pier handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Pier?
The Pier was 48% built at the site inspection on 20 October 2026. The site has been inspected 7 times since June 2024. The Land Department took 46 site photos at its inspections.
Is The Pier delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building The Pier?
The registered developer is Continental Investments Lmd. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for The Pier?
The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.