The Pier construction progress

The Pier in Dubai Maritime City is 35% built at the Land Department inspection of July 2026. Developer Continental Investments Lmd. Completion registered for December 2026.

35%

Built, at the Land Department site inspection of 14 July 2026

Running behind its date

Completion date (Land Department)
December 2026
Finish at recent pace
January 2029
Construction started
July 2024
Registered with the Land Department
July 2024
Units
282
Escrow bank
The National Bank of Fujairah
Name in Arabic
ذا بير
Land Department project number
3110
Land Department site inspections
6

Schedule

Between August 2025 and July 2026 the site added about 2.2 points a month. At that rate it would finish around January 2029, more than three months after the December 2026 date registered with the Land Department.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

14 July 2026

35%+8.6 pts

  • The Pier construction site, Land Department inspection photo 1, 14 July 2026
  • The Pier construction site, Land Department inspection photo 2, 14 July 2026
  • The Pier construction site, Land Department inspection photo 3, 14 July 2026
  • The Pier construction site, Land Department inspection photo 4, 14 July 2026

10 April 2026

26%+6.3 pts

  • The Pier construction site, Land Department inspection photo 1, 10 April 2026
  • The Pier construction site, Land Department inspection photo 2, 10 April 2026
  • The Pier construction site, Land Department inspection photo 3, 10 April 2026
  • The Pier construction site, Land Department inspection photo 4, 10 April 2026

15 December 2025

20%+8.0 pts

  • The Pier construction site, Land Department inspection photo 1, 15 December 2025
  • The Pier construction site, Land Department inspection photo 2, 15 December 2025
  • The Pier construction site, Land Department inspection photo 3, 15 December 2025
  • The Pier construction site, Land Department inspection photo 4, 15 December 2025

26 August 2025

12%+6.6 pts

  • The Pier construction site, Land Department inspection photo 1, 26 August 2025
  • The Pier construction site, Land Department inspection photo 2, 26 August 2025
  • The Pier construction site, Land Department inspection photo 3, 26 August 2025
  • The Pier construction site, Land Department inspection photo 4, 26 August 2025

2 April 2025

5.4%+5.4 pts

  • The Pier construction site, Land Department inspection photo 1, 2 April 2025
  • The Pier construction site, Land Department inspection photo 2, 2 April 2025
  • The Pier construction site, Land Department inspection photo 3, 2 April 2025

27 June 2024

0%

  • The Pier construction site, Land Department inspection photo 1, 27 June 2024

All 34 site photos, by inspection date

Context

Dubai Maritime City has 23 projects under construction, 29% built on average.

Continental Investments Lmd has 4 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Pier?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will The Pier be completed?
The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around January 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Pier is built?
35%, measured at the Land Department site inspection on 14 July 2026. The Land Department engineers have inspected the site 6 times since June 2024.
Is The Pier delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building The Pier?
The registered developer is Continental Investments Lmd. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for The Pier?
The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.