The Pier construction progress
The Pier in Dubai Maritime City is 35% built at the Land Department inspection of July 2026. Developer Continental Investments Lmd. Completion registered for December 2026.
35%
Built, at the Land Department site inspection of 14 July 2026
Running behind its date
- Completion date (Land Department)
- December 2026
- Finish at recent pace
- January 2029
- Construction started
- July 2024
- Registered with the Land Department
- July 2024
- Developer
- Continental Investments Lmd
- Community
- Dubai Maritime City
- Units
- 282
- Escrow bank
- The National Bank of Fujairah
- Name in Arabic
- ذا بير
- Land Department project number
- 3110
- Land Department site inspections
- 6
Schedule
Between August 2025 and July 2026 the site added about 2.2 points a month. At that rate it would finish around January 2029, more than three months after the December 2026 date registered with the Land Department.
Site inspections
14 July 2026
35%+8.6 pts
10 April 2026
26%+6.3 pts
15 December 2025
20%+8.0 pts
26 August 2025
12%+6.6 pts
2 April 2025
5.4%+5.4 pts
27 June 2024
0%
Context
Dubai Maritime City has 23 projects under construction, 29% built on average.
Continental Investments Lmd has 4 projects under construction in Dubai, none past their registered completion dates.
Own a unit in The Pier?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will The Pier be completed?
- The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around January 2029. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of The Pier is built?
- 35%, measured at the Land Department site inspection on 14 July 2026. The Land Department engineers have inspected the site 6 times since June 2024.
- Is The Pier delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building The Pier?
- The registered developer is Continental Investments Lmd. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for The Pier?
- The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Boutique 23Also by Continental Investments Lmd. 49%.
- La BoutiqueAlso by Continental Investments Lmd. 38%, Due December 2026.
- Taiyo ResidencesAlso by Continental Investments Lmd. 5.1%, Due December 2027.
- Harbour LightsNearby in Dubai Maritime City. 64%, Due May 2027.
- Mar CasaNearby in Dubai Maritime City. 56%, Due October 2026.
- Aria By BeyondNearby in Dubai Maritime City. 85%, Due January 2026, passed.
- Coral ReefNearby in Dubai Maritime City. 33%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)