The Edit At D3 construction progress
The registered completion date for The Edit At D3 is January 2030. At the last site inspection, in August 2026, it was 0.2% built. The developer is Dhre 2 Bts.
0.2%
Built, at the site inspection of 19 August 2026
Running behind its date
- Registered completion date
- January 2030
- Finish at recent pace
- March 2361
- Construction started
- January 2026
- First registered
- November 2025
- Developer
- Dhre 2 Bts
- Units
- 557
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- D3 ذا إيديت في
- Project number
- 4177
- Site inspections
- 3
Schedule
Between October 2025 and August 2026 the site added about 0.0 points a month. At that rate it would finish around March 2361, more than three months after its registered date of January 2030.
Site inspections
19 August 2026
0.2%+0.2 pts
1 June 2026
0%
29 October 2025
0%
Context
Dhre 2 Bts has 12 projects under construction in Dubai, none past their registered completion dates.
Own a unit in The Edit At D3?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the The Edit At D3 handover date?
- The registered completion date is January 2030. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2361. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on The Edit At D3?
- The Edit At D3 was 0.2% built at the site inspection on 19 August 2026. The site has been inspected 3 times since October 2025. The Land Department took 8 site photos at its inspections.
- Is The Edit At D3 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2030.
- Who is building The Edit At D3?
- The registered developer is Dhre 2 Bts. It has 11 other projects under construction in Dubai.
- Which bank holds the escrow account for The Edit At D3?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Bulgari Lighthouse DubaiAlso by Dhre 2 Bts. 80%, Due March 2027.
- Bluewaters BayAlso by Dhre 2 Bts. 37%, Due March 2027.
- Design QuarterAlso by Dhre 2 Bts. 41%, Due February 2027.
- The AcresAlso by Dhre 2 Bts. 38%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)