Skip to content

The Rings construction progress

The Rings in Dubai Water Canal was registered to complete in December 2025 and is still under construction. At the last site inspection, in August 2026, it was 35% built. The developer is P M R Development.

35%

Built, at the site inspection of 26 August 2026

11 months past its registered completion date

Registered completion date
December 2025
Finish at recent pace
November 2029
Construction started
January 2024
First registered
October 2023
Developer
P M R Development
Units
13
Escrow bank
Commercial Bank of Dubai
Name in Arabic
الخواتم
Project number
2767
Site inspections
9

Schedule

The Rings was registered to complete in December 2025, 11 months ago, and is still under construction. Over the last year of inspections it has added about 1.7 points a month. Kept at that rate, the site would reach 100% around November 2029.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

26 August 2026

35%+6.5 pts

  • The Rings construction site, inspection photo 1, 26 August 2026
  • The Rings construction site, inspection photo 2, 26 August 2026
  • The Rings construction site, inspection photo 3, 26 August 2026
  • The Rings construction site, inspection photo 4, 26 August 2026

8 June 2026

29%+4.3 pts

  • The Rings construction site, inspection photo 1, 8 June 2026
  • The Rings construction site, inspection photo 2, 8 June 2026
  • The Rings construction site, inspection photo 3, 8 June 2026
  • The Rings construction site, inspection photo 4, 8 June 2026

25 March 2026

24%+3.5 pts

  • The Rings construction site, inspection photo 1, 25 March 2026
  • The Rings construction site, inspection photo 2, 25 March 2026
  • The Rings construction site, inspection photo 3, 25 March 2026
  • The Rings construction site, inspection photo 4, 25 March 2026

11 December 2025

21%+8.8 pts

  • The Rings construction site, inspection photo 1, 11 December 2025
  • The Rings construction site, inspection photo 2, 11 December 2025
  • The Rings construction site, inspection photo 3, 11 December 2025
  • The Rings construction site, inspection photo 4, 11 December 2025

28 July 2025

12%+3.3 pts

  • The Rings construction site, inspection photo 1, 28 July 2025
  • The Rings construction site, inspection photo 2, 28 July 2025
  • The Rings construction site, inspection photo 3, 28 July 2025
  • The Rings construction site, inspection photo 4, 28 July 2025

15 May 2025

8.7%+2.0 pts

  • The Rings construction site, inspection photo 1, 15 May 2025
  • The Rings construction site, inspection photo 2, 15 May 2025
  • The Rings construction site, inspection photo 3, 15 May 2025
  • The Rings construction site, inspection photo 4, 15 May 2025

22 January 2025

6.6%+3.9 pts

  • The Rings construction site, inspection photo 1, 22 January 2025
  • The Rings construction site, inspection photo 2, 22 January 2025
  • The Rings construction site, inspection photo 3, 22 January 2025

21 May 2024

2.7%+2.7 pts

  • The Rings construction site, inspection photo 1, 21 May 2024
  • The Rings construction site, inspection photo 2, 21 May 2024
  • The Rings construction site, inspection photo 3, 21 May 2024
  • The Rings construction site, inspection photo 4, 21 May 2024

21 September 2023

0%

  • The Rings construction site, inspection photo 1, 21 September 2023
  • The Rings construction site, inspection photo 2, 21 September 2023
  • The Rings construction site, inspection photo 3, 21 September 2023

All 46 site photos, by inspection date

Context

Dubai Water Canal has 11 projects under construction, 38% built on average.

Own a unit in The Rings?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Rings handover date?
The registered completion date was December 2025, and the register still lists The Rings as under construction. At the pace of its recent inspections the site would reach 100% around November 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Rings?
The Rings was 35% built at the site inspection on 26 August 2026. The site has been inspected 9 times since September 2023. The Land Department took 46 site photos at its inspections.
Is The Rings delayed?
Yes. Its registered completion date of December 2025 has passed and the project is still listed as under construction.
Who is building The Rings?
The registered developer is P M R Development.
Which bank holds the escrow account for The Rings?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.