Casa Canal construction progress

Casa Canal in Dubai Water Canal is 38% built at the Land Department inspection of September 2026. Developer Ahs Canal Two Real Estate Development.

38%

Built, at the Land Department site inspection of 17 September 2026

Finish at recent pace
September 2028
Construction started
October 2023
Registered with the Land Department
September 2023
Developer
Ahs Canal Two Real Estate Development
Units
68
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
كازا قنال
Land Department project number
2679
Land Department site inspections
8

Schedule

Since January 2026 Casa Canal has added about 2.5 points a month. At that rate the site reaches 100% around September 2028. The Land Department has no completion date on record to compare it with.

0%25%50%75%100%202420252026
Progress at each Land Department site inspection

Site inspections

17 September 2026

38%+7.5 pts

  • Casa Canal construction site, Land Department inspection photo 1, 17 September 2026
  • Casa Canal construction site, Land Department inspection photo 2, 17 September 2026
  • Casa Canal construction site, Land Department inspection photo 3, 17 September 2026
  • Casa Canal construction site, Land Department inspection photo 4, 17 September 2026

24 June 2026

31%+10 pts

  • Casa Canal construction site, Land Department inspection photo 1, 24 June 2026
  • Casa Canal construction site, Land Department inspection photo 2, 24 June 2026
  • Casa Canal construction site, Land Department inspection photo 3, 24 June 2026
  • Casa Canal construction site, Land Department inspection photo 4, 24 June 2026

18 March 2026

21%+3.3 pts

  • Casa Canal construction site, Land Department inspection photo 1, 18 March 2026
  • Casa Canal construction site, Land Department inspection photo 2, 18 March 2026
  • Casa Canal construction site, Land Department inspection photo 3, 18 March 2026
  • Casa Canal construction site, Land Department inspection photo 4, 18 March 2026

7 January 2026

17%+5.1 pts

  • Casa Canal construction site, Land Department inspection photo 1, 7 January 2026
  • Casa Canal construction site, Land Department inspection photo 2, 7 January 2026
  • Casa Canal construction site, Land Department inspection photo 3, 7 January 2026
  • Casa Canal construction site, Land Department inspection photo 4, 7 January 2026

15 May 2025

12%+4.7 pts

  • Casa Canal construction site, Land Department inspection photo 1, 15 May 2025
  • Casa Canal construction site, Land Department inspection photo 2, 15 May 2025
  • Casa Canal construction site, Land Department inspection photo 3, 15 May 2025
  • Casa Canal construction site, Land Department inspection photo 4, 15 May 2025

10 October 2024

7.4%+5.7 pts

  • Casa Canal construction site, Land Department inspection photo 1, 10 October 2024
  • Casa Canal construction site, Land Department inspection photo 2, 10 October 2024
  • Casa Canal construction site, Land Department inspection photo 3, 10 October 2024
  • Casa Canal construction site, Land Department inspection photo 4, 10 October 2024

11 June 2024

1.7%+1.7 pts

  • Casa Canal construction site, Land Department inspection photo 1, 11 June 2024
  • Casa Canal construction site, Land Department inspection photo 2, 11 June 2024
  • Casa Canal construction site, Land Department inspection photo 3, 11 June 2024

9 June 2023

0%

  • Casa Canal construction site, Land Department inspection photo 1, 9 June 2023
  • Casa Canal construction site, Land Department inspection photo 2, 9 June 2023

All 38 site photos, by inspection date

Context

Dubai Water Canal has 10 projects under construction, 37% built on average. Casa Canal is ahead of that average.

Own a unit in Casa Canal?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Casa Canal be completed?
The Land Department has no completion date on record for Casa Canal yet. It appears once the developer registers the construction timeline.
How much of Casa Canal is built?
38%, measured at the Land Department site inspection on 17 September 2026. The Land Department engineers have inspected the site 8 times since June 2023.
Who is building Casa Canal?
The registered developer is Ahs Canal Two Real Estate Development.
Which bank holds the escrow account for Casa Canal?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.