Casa Canal construction progress

No completion date is registered for Casa Canal in Dubai Water Canal yet. At the last site inspection, in October 2026, it was 43% built. The developer is Ahs Canal Two Real Estate Development.

43%

Built, at the site inspection of 28 October 2026

Finish at recent pace
August 2028
Construction started
October 2023
First registered
September 2023
Developer
Ahs Canal Two Real Estate Development
Units
68
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
كازا قنال
Project number
2679
Site inspections
9

Schedule

Since January 2026 Casa Canal has added about 2.7 points a month. At that rate the site reaches 100% around August 2028. No completion date is on record to compare it with.

0%25%50%75%100%202420252026
Progress at each site inspection

Site inspections

28 October 2026

43%+4.5 pts

  • Casa Canal construction site, inspection photo 1, 28 October 2026
  • Casa Canal construction site, inspection photo 2, 28 October 2026
  • Casa Canal construction site, inspection photo 3, 28 October 2026
  • Casa Canal construction site, inspection photo 4, 28 October 2026

17 September 2026

38%+7.5 pts

  • Casa Canal construction site, inspection photo 1, 17 September 2026
  • Casa Canal construction site, inspection photo 2, 17 September 2026
  • Casa Canal construction site, inspection photo 3, 17 September 2026
  • Casa Canal construction site, inspection photo 4, 17 September 2026

24 June 2026

31%+10 pts

  • Casa Canal construction site, inspection photo 1, 24 June 2026
  • Casa Canal construction site, inspection photo 2, 24 June 2026
  • Casa Canal construction site, inspection photo 3, 24 June 2026
  • Casa Canal construction site, inspection photo 4, 24 June 2026

18 March 2026

21%+3.3 pts

  • Casa Canal construction site, inspection photo 1, 18 March 2026
  • Casa Canal construction site, inspection photo 2, 18 March 2026
  • Casa Canal construction site, inspection photo 3, 18 March 2026
  • Casa Canal construction site, inspection photo 4, 18 March 2026

7 January 2026

17%+5.1 pts

  • Casa Canal construction site, inspection photo 1, 7 January 2026
  • Casa Canal construction site, inspection photo 2, 7 January 2026
  • Casa Canal construction site, inspection photo 3, 7 January 2026
  • Casa Canal construction site, inspection photo 4, 7 January 2026

15 May 2025

12%+4.7 pts

  • Casa Canal construction site, inspection photo 1, 15 May 2025
  • Casa Canal construction site, inspection photo 2, 15 May 2025
  • Casa Canal construction site, inspection photo 3, 15 May 2025
  • Casa Canal construction site, inspection photo 4, 15 May 2025

10 October 2024

7.4%+5.7 pts

  • Casa Canal construction site, inspection photo 1, 10 October 2024
  • Casa Canal construction site, inspection photo 2, 10 October 2024
  • Casa Canal construction site, inspection photo 3, 10 October 2024
  • Casa Canal construction site, inspection photo 4, 10 October 2024

11 June 2024

1.7%+1.7 pts

  • Casa Canal construction site, inspection photo 1, 11 June 2024
  • Casa Canal construction site, inspection photo 2, 11 June 2024
  • Casa Canal construction site, inspection photo 3, 11 June 2024

9 June 2023

0%

  • Casa Canal construction site, inspection photo 1, 9 June 2023
  • Casa Canal construction site, inspection photo 2, 9 June 2023

All 50 site photos, by inspection date

Context

Dubai Water Canal has 11 projects under construction, 38% built on average.

Own a unit in Casa Canal?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Casa Canal handover date?
No completion date is on record for Casa Canal yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Casa Canal?
Casa Canal was 43% built at the site inspection on 28 October 2026. The site has been inspected 9 times since June 2023. The Land Department took 50 site photos at its inspections.
Who is building Casa Canal?
The registered developer is Ahs Canal Two Real Estate Development.
Which bank holds the escrow account for Casa Canal?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.