Casa Canal construction progress
Casa Canal in Dubai Water Canal is 38% built at the Land Department inspection of September 2026. Developer Ahs Canal Two Real Estate Development.
38%
Built, at the Land Department site inspection of 17 September 2026
- Finish at recent pace
- September 2028
- Construction started
- October 2023
- Registered with the Land Department
- September 2023
- Developer
- Ahs Canal Two Real Estate Development
- Community
- Dubai Water Canal
- Units
- 68
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- كازا قنال
- Land Department project number
- 2679
- Land Department site inspections
- 8
Schedule
Since January 2026 Casa Canal has added about 2.5 points a month. At that rate the site reaches 100% around September 2028. The Land Department has no completion date on record to compare it with.
Site inspections
17 September 2026
38%+7.5 pts
24 June 2026
31%+10 pts
18 March 2026
21%+3.3 pts
7 January 2026
17%+5.1 pts
15 May 2025
12%+4.7 pts
10 October 2024
7.4%+5.7 pts
11 June 2024
1.7%+1.7 pts
9 June 2023
0%
Context
Dubai Water Canal has 10 projects under construction, 37% built on average. Casa Canal is ahead of that average.
Own a unit in Casa Canal?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Casa Canal be completed?
- The Land Department has no completion date on record for Casa Canal yet. It appears once the developer registers the construction timeline.
- How much of Casa Canal is built?
- 38%, measured at the Land Department site inspection on 17 September 2026. The Land Department engineers have inspected the site 8 times since June 2023.
- Who is building Casa Canal?
- The registered developer is Ahs Canal Two Real Estate Development.
- Which bank holds the escrow account for Casa Canal?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Damac CityNearby in Dubai Water Canal. 73%, Due December 2025, passed.
- Cavalli CoutureNearby in Dubai Water Canal. 20%, Due May 2025, passed.
- One CanalNearby in Dubai Water Canal. 77%.
- The MelgranoNearby in Dubai Water Canal. 32%, Due December 2026.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)