One Canal construction progress
One Canal in Dubai Water Canal was registered to complete in May 2025 and is still under construction. At the last site inspection, in October 2026, it was 88% built. The developer is A H S Canal Development.
88%
Built, at the site inspection of 23 October 2026
18 months past its registered completion date
- Registered completion date
- May 2025
- Finish at recent pace
- March 2027
- Construction started
- December 2022
- First registered
- November 2022
- Developer
- A H S Canal Development
- Community
- Dubai Water Canal
- Units
- 44
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- وان كانال
- Project number
- 2501
- Site inspections
- 14
Schedule
One Canal was registered to complete in May 2025, 18 months ago, and is still under construction. Over the last year of inspections it has added about 2.9 points a month. Kept at that rate, the site would reach 100% around March 2027.
Site inspections
23 October 2026
88%+10 pts
28 July 2026
77%+8.8 pts
14 April 2026
69%+5.2 pts
11 February 2026
63%+5.9 pts
5 December 2025
58%+14 pts
21 August 2025
44%+10 pts
14 May 2025
34%+11 pts
19 December 2024
23%+4.1 pts
8 October 2024
19%+3.9 pts
19 August 2024
15%+6.3 pts
Context
Dubai Water Canal has 11 projects under construction, 38% built on average.
Own a unit in One Canal?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the One Canal handover date?
- The registered completion date was May 2025, and the register still lists One Canal as under construction. At the pace of its recent inspections the site would reach 100% around March 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on One Canal?
- One Canal was 88% built at the site inspection on 23 October 2026. The site has been inspected 14 times since November 2022. The Land Department took 91 site photos at its inspections.
- Is One Canal delayed?
- Yes. Its registered completion date of May 2025 has passed and the project is still listed as under construction.
- Who is building One Canal?
- The registered developer is A H S Canal Development.
- Which bank holds the escrow account for One Canal?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Damac CityNearby in Dubai Water Canal. 73%, Due December 2025, passed.
- Cavalli CoutureNearby in Dubai Water Canal. 28%, Due May 2025, passed.
- Casa CanalNearby in Dubai Water Canal. 43%.
- The MelgranoNearby in Dubai Water Canal. 43%, Due December 2026.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)