Cavalli Couture construction progress
Cavalli Couture in Dubai Water Canal is 20% built at the Land Department inspection of April 2026. Developer Damac Business Real Estate Co. Completion registered for May 2025.
20%
Built, at the Land Department site inspection of 8 April 2026
16 months past its registered completion date
- Completion date (Land Department)
- May 2025
- Finish at recent pace
- January 2034
- Construction started
- March 2023
- Registered with the Land Department
- October 2022
- Developer
- Damac Business Real Estate Co
- Community
- Dubai Water Canal
- Units
- 95
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- كفالي كوتور
- Land Department project number
- 2459
- Land Department site inspections
- 9
Schedule
Cavalli Couture was registered to complete in May 2025, 16 months ago, and is still under construction. Over the last year of inspections it has added about 0.9 points a month. Kept at that rate, the site would reach 100% around January 2034.
Site inspections
8 April 2026
20%+4.8 pts
23 December 2025
15%+4.0 pts
30 May 2025
11%+5.0 pts
5 July 2024
5.9%+2.2 pts
29 May 2024
3.6%+0.3 pts
15 November 2023
3.3%+1.0 pts
4 July 2023
2.3%+1.6 pts
11 April 2023
0.7%+0.7 pts
15 September 2022
0%
Context
Dubai Water Canal has 10 projects under construction, 37% built on average.
Own a unit in Cavalli Couture?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Cavalli Couture be completed?
- The completion date registered with the Dubai Land Department is May 2025. At the pace of its recent inspections the site would reach 100% around January 2034. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Cavalli Couture is built?
- 20%, measured at the Land Department site inspection on 8 April 2026. The Land Department engineers have inspected the site 9 times since September 2022.
- Is Cavalli Couture delayed?
- Yes. Its registered completion date of May 2025 has passed and the Land Department still lists it as under construction.
- Who is building Cavalli Couture?
- The registered developer is Damac Business Real Estate Co.
- Which bank holds the escrow account for Cavalli Couture?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Damac CityNearby in Dubai Water Canal. 73%, Due December 2025, passed.
- One CanalNearby in Dubai Water Canal. 77%.
- Casa CanalNearby in Dubai Water Canal. 38%.
- The MelgranoNearby in Dubai Water Canal. 32%, Due December 2026.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)






.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)