Cavalli Couture construction progress
Cavalli Couture in Dubai Water Canal was registered to complete in May 2025 and is still under construction. At the last site inspection, in November 2026, it was 28% built. The developer is Damac Business Real Estate Co.
28%
Built, at the site inspection of 4 November 2026
18 months past its registered completion date
- Registered completion date
- May 2025
- Finish at recent pace
- October 2031
- Construction started
- March 2023
- First registered
- October 2022
- Developer
- Damac Business Real Estate Co
- Community
- Dubai Water Canal
- Units
- 95
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- كفالي كوتور
- Project number
- 2459
- Site inspections
- 10
Schedule
Cavalli Couture was registered to complete in May 2025, 18 months ago, and is still under construction. Over the last year of inspections it has added about 1.2 points a month. Kept at that rate, the site would reach 100% around October 2031.
Site inspections
4 November 2026
28%+7.9 pts
8 April 2026
20%+4.8 pts
23 December 2025
15%+4.0 pts
30 May 2025
11%+5.0 pts
5 July 2024
5.9%+2.2 pts
29 May 2024
3.6%+0.3 pts
15 November 2023
3.3%+1.0 pts
4 July 2023
2.3%+1.6 pts
11 April 2023
0.7%+0.7 pts
15 September 2022
0%
Context
Dubai Water Canal has 11 projects under construction, 38% built on average.
Own a unit in Cavalli Couture?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Cavalli Couture handover date?
- The registered completion date was May 2025, and the register still lists Cavalli Couture as under construction. At the pace of its recent inspections the site would reach 100% around October 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Cavalli Couture?
- Cavalli Couture was 28% built at the site inspection on 4 November 2026. The site has been inspected 10 times since September 2022. The Land Department took 46 site photos at its inspections.
- Is Cavalli Couture delayed?
- Yes. Its registered completion date of May 2025 has passed and the project is still listed as under construction.
- Who is building Cavalli Couture?
- The registered developer is Damac Business Real Estate Co.
- Which bank holds the escrow account for Cavalli Couture?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Damac CityNearby in Dubai Water Canal. 73%, Due December 2025, passed.
- One CanalNearby in Dubai Water Canal. 88%, Due May 2025, passed.
- Casa CanalNearby in Dubai Water Canal. 43%.
- The MelgranoNearby in Dubai Water Canal. 43%, Due December 2026.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.








.jpeg&w=3840&q=75)



.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)






.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)