Cavalli Couture construction progress

Cavalli Couture in Dubai Water Canal is 20% built at the Land Department inspection of April 2026. Developer Damac Business Real Estate Co. Completion registered for May 2025.

20%

Built, at the Land Department site inspection of 8 April 2026

16 months past its registered completion date

Completion date (Land Department)
May 2025
Finish at recent pace
January 2034
Construction started
March 2023
Registered with the Land Department
October 2022
Developer
Damac Business Real Estate Co
Units
95
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
كفالي كوتور
Land Department project number
2459
Land Department site inspections
9

Schedule

Cavalli Couture was registered to complete in May 2025, 16 months ago, and is still under construction. Over the last year of inspections it has added about 0.9 points a month. Kept at that rate, the site would reach 100% around January 2034.

0%25%50%75%100%2023202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

8 April 2026

20%+4.8 pts

  • Cavalli Couture construction site, Land Department inspection photo 1, 8 April 2026
  • Cavalli Couture construction site, Land Department inspection photo 2, 8 April 2026
  • Cavalli Couture construction site, Land Department inspection photo 3, 8 April 2026
  • Cavalli Couture construction site, Land Department inspection photo 4, 8 April 2026

23 December 2025

15%+4.0 pts

  • Cavalli Couture construction site, Land Department inspection photo 1, 23 December 2025
  • Cavalli Couture construction site, Land Department inspection photo 2, 23 December 2025
  • Cavalli Couture construction site, Land Department inspection photo 3, 23 December 2025
  • Cavalli Couture construction site, Land Department inspection photo 4, 23 December 2025

30 May 2025

11%+5.0 pts

  • Cavalli Couture construction site, Land Department inspection photo 1, 30 May 2025
  • Cavalli Couture construction site, Land Department inspection photo 2, 30 May 2025
  • Cavalli Couture construction site, Land Department inspection photo 3, 30 May 2025
  • Cavalli Couture construction site, Land Department inspection photo 4, 30 May 2025

5 July 2024

5.9%+2.2 pts

  • Cavalli Couture construction site, Land Department inspection photo 1, 5 July 2024
  • Cavalli Couture construction site, Land Department inspection photo 2, 5 July 2024
  • Cavalli Couture construction site, Land Department inspection photo 3, 5 July 2024
  • Cavalli Couture construction site, Land Department inspection photo 4, 5 July 2024

29 May 2024

3.6%+0.3 pts

  • Cavalli Couture construction site, Land Department inspection photo 1, 29 May 2024
  • Cavalli Couture construction site, Land Department inspection photo 2, 29 May 2024

15 November 2023

3.3%+1.0 pts

  • Cavalli Couture construction site, Land Department inspection photo 1, 15 November 2023
  • Cavalli Couture construction site, Land Department inspection photo 2, 15 November 2023
  • Cavalli Couture construction site, Land Department inspection photo 3, 15 November 2023

4 July 2023

2.3%+1.6 pts

  • Cavalli Couture construction site, Land Department inspection photo 1, 4 July 2023
  • Cavalli Couture construction site, Land Department inspection photo 2, 4 July 2023
  • Cavalli Couture construction site, Land Department inspection photo 3, 4 July 2023
  • Cavalli Couture construction site, Land Department inspection photo 4, 4 July 2023

11 April 2023

0.7%+0.7 pts

  • Cavalli Couture construction site, Land Department inspection photo 1, 11 April 2023
  • Cavalli Couture construction site, Land Department inspection photo 2, 11 April 2023
  • Cavalli Couture construction site, Land Department inspection photo 3, 11 April 2023
  • Cavalli Couture construction site, Land Department inspection photo 4, 11 April 2023

15 September 2022

0%

  • Cavalli Couture construction site, Land Department inspection photo 1, 15 September 2022
  • Cavalli Couture construction site, Land Department inspection photo 2, 15 September 2022
  • Cavalli Couture construction site, Land Department inspection photo 3, 15 September 2022

All 38 site photos, by inspection date

Context

Dubai Water Canal has 10 projects under construction, 37% built on average.

Own a unit in Cavalli Couture?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Cavalli Couture be completed?
The completion date registered with the Dubai Land Department is May 2025. At the pace of its recent inspections the site would reach 100% around January 2034. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Cavalli Couture is built?
20%, measured at the Land Department site inspection on 8 April 2026. The Land Department engineers have inspected the site 9 times since September 2022.
Is Cavalli Couture delayed?
Yes. Its registered completion date of May 2025 has passed and the Land Department still lists it as under construction.
Who is building Cavalli Couture?
The registered developer is Damac Business Real Estate Co.
Which bank holds the escrow account for Cavalli Couture?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.