Damac City construction progress
Damac City in Dubai Water Canal was registered to complete in December 2025 and is still under construction. At the last site inspection, in September 2026, it was 73% built. The developer is J A Parks.
73%
Built, at the site inspection of 30 September 2026
11 months past its registered completion date
- Registered completion date
- December 2025
- Finish at recent pace
- July 2027
- Construction started
- June 2022
- First registered
- March 2022
- Developer
- J A Parks
- Community
- Dubai Water Canal
- Units
- 511
- Escrow bank
- Emirates NBD
- Name in Arabic
- داماك سيتي
- Project number
- 2374
- Site inspections
- 13
Schedule
Damac City was registered to complete in December 2025, 11 months ago, and is still under construction. Over the last year of inspections it has added about 2.9 points a month. Kept at that rate, the site would reach 100% around July 2027.
Site inspections
30 September 2026
73%+4.1 pts
15 July 2026
69%+9.8 pts
24 March 2026
59%+17 pts
15 November 2025
42%+4.1 pts
4 July 2025
38%+14 pts
1 February 2025
24%+3.6 pts
18 October 2024
20%+6.6 pts
20 June 2024
13%+3.3 pts
25 March 2024
10%+4.0 pts
15 August 2023
6.2%+0.2 pts
Context
Dubai Water Canal has 11 projects under construction, 38% built on average.
Own a unit in Damac City?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Damac City handover date?
- The registered completion date was December 2025, and the register still lists Damac City as under construction. At the pace of its recent inspections the site would reach 100% around July 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Damac City?
- Damac City was 73% built at the site inspection on 30 September 2026. The site has been inspected 13 times since September 2022. The Land Department took 89 site photos at its inspections.
- Is Damac City delayed?
- Yes. Its registered completion date of December 2025 has passed and the project is still listed as under construction.
- Who is building Damac City?
- The registered developer is J A Parks.
- Which bank holds the escrow account for Damac City?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Cavalli CoutureNearby in Dubai Water Canal. 28%, Due May 2025, passed.
- One CanalNearby in Dubai Water Canal. 88%, Due May 2025, passed.
- Casa CanalNearby in Dubai Water Canal. 43%.
- The MelgranoNearby in Dubai Water Canal. 43%, Due December 2026.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.








.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)







.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)