Damac City construction progress

Damac City in Dubai Water Canal was registered to complete in December 2025 and is still under construction. At the last site inspection, in September 2026, it was 73% built. The developer is J A Parks.

73%

Built, at the site inspection of 30 September 2026

11 months past its registered completion date

Registered completion date
December 2025
Finish at recent pace
July 2027
Construction started
June 2022
First registered
March 2022
Developer
J A Parks
Units
511
Escrow bank
Emirates NBD
Name in Arabic
داماك سيتي
Project number
2374
Site inspections
13

Schedule

Damac City was registered to complete in December 2025, 11 months ago, and is still under construction. Over the last year of inspections it has added about 2.9 points a month. Kept at that rate, the site would reach 100% around July 2027.

0%25%50%75%100%2023202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

30 September 2026

73%+4.1 pts

  • Damac City construction site, inspection photo 1, 30 September 2026
  • Damac City construction site, inspection photo 2, 30 September 2026
  • Damac City construction site, inspection photo 3, 30 September 2026
  • Damac City construction site, inspection photo 4, 30 September 2026

15 July 2026

69%+9.8 pts

  • Damac City construction site, inspection photo 1, 15 July 2026
  • Damac City construction site, inspection photo 2, 15 July 2026
  • Damac City construction site, inspection photo 3, 15 July 2026
  • Damac City construction site, inspection photo 4, 15 July 2026

24 March 2026

59%+17 pts

  • Damac City construction site, inspection photo 1, 24 March 2026
  • Damac City construction site, inspection photo 2, 24 March 2026
  • Damac City construction site, inspection photo 3, 24 March 2026
  • Damac City construction site, inspection photo 4, 24 March 2026

15 November 2025

42%+4.1 pts

  • Damac City construction site, inspection photo 1, 15 November 2025
  • Damac City construction site, inspection photo 2, 15 November 2025
  • Damac City construction site, inspection photo 3, 15 November 2025
  • Damac City construction site, inspection photo 4, 15 November 2025

4 July 2025

38%+14 pts

  • Damac City construction site, inspection photo 1, 4 July 2025
  • Damac City construction site, inspection photo 2, 4 July 2025
  • Damac City construction site, inspection photo 3, 4 July 2025
  • Damac City construction site, inspection photo 4, 4 July 2025

1 February 2025

24%+3.6 pts

  • Damac City construction site, inspection photo 1, 1 February 2025
  • Damac City construction site, inspection photo 2, 1 February 2025
  • Damac City construction site, inspection photo 3, 1 February 2025
  • Damac City construction site, inspection photo 4, 1 February 2025

18 October 2024

20%+6.6 pts

  • Damac City construction site, inspection photo 1, 18 October 2024
  • Damac City construction site, inspection photo 2, 18 October 2024
  • Damac City construction site, inspection photo 3, 18 October 2024
  • Damac City construction site, inspection photo 4, 18 October 2024

20 June 2024

13%+3.3 pts

  • Damac City construction site, inspection photo 1, 20 June 2024
  • Damac City construction site, inspection photo 2, 20 June 2024
  • Damac City construction site, inspection photo 3, 20 June 2024
  • Damac City construction site, inspection photo 4, 20 June 2024

25 March 2024

10%+4.0 pts

  • Damac City construction site, inspection photo 1, 25 March 2024
  • Damac City construction site, inspection photo 2, 25 March 2024
  • Damac City construction site, inspection photo 3, 25 March 2024

15 August 2023

6.2%+0.2 pts

  • Damac City construction site, inspection photo 1, 15 August 2023
  • Damac City construction site, inspection photo 2, 15 August 2023
  • Damac City construction site, inspection photo 3, 15 August 2023
  • Damac City construction site, inspection photo 4, 15 August 2023

All 89 site photos, by inspection date

Context

Dubai Water Canal has 11 projects under construction, 38% built on average.

Own a unit in Damac City?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Damac City handover date?
The registered completion date was December 2025, and the register still lists Damac City as under construction. At the pace of its recent inspections the site would reach 100% around July 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Damac City?
Damac City was 73% built at the site inspection on 30 September 2026. The site has been inspected 13 times since September 2022. The Land Department took 89 site photos at its inspections.
Is Damac City delayed?
Yes. Its registered completion date of December 2025 has passed and the project is still listed as under construction.
Who is building Damac City?
The registered developer is J A Parks.
Which bank holds the escrow account for Damac City?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.