Damac City construction progress
Damac City in Dubai Water Canal is 73% built at the Land Department inspection of September 2026. Developer J A Parks. Completion registered for December 2025.
73%
Built, at the Land Department site inspection of 30 September 2026
9 months past its registered completion date
- Completion date (Land Department)
- December 2025
- Finish at recent pace
- July 2027
- Construction started
- June 2022
- Registered with the Land Department
- March 2022
- Developer
- J A Parks
- Community
- Dubai Water Canal
- Units
- 511
- Escrow bank
- Emirates NBD
- Name in Arabic
- داماك سيتي
- Land Department project number
- 2374
- Land Department site inspections
- 13
Schedule
Damac City was registered to complete in December 2025, 9 months ago, and is still under construction. Over the last year of inspections it has added about 2.9 points a month. Kept at that rate, the site would reach 100% around July 2027.
Site inspections
30 September 2026
73%+4.1 pts
15 July 2026
69%+9.8 pts
24 March 2026
59%+17 pts
15 November 2025
42%+4.1 pts
4 July 2025
38%+14 pts
1 February 2025
24%+3.6 pts
18 October 2024
20%+6.6 pts
20 June 2024
13%+3.3 pts
25 March 2024
10%+4.0 pts
15 August 2023
6.2%+0.2 pts
Context
Dubai Water Canal has 10 projects under construction, 37% built on average.
Own a unit in Damac City?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Damac City be completed?
- The completion date registered with the Dubai Land Department is December 2025. At the pace of its recent inspections the site would reach 100% around July 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Damac City is built?
- 73%, measured at the Land Department site inspection on 30 September 2026. The Land Department engineers have inspected the site 13 times since September 2022.
- Is Damac City delayed?
- Yes. Its registered completion date of December 2025 has passed and the Land Department still lists it as under construction.
- Who is building Damac City?
- The registered developer is J A Parks.
- Which bank holds the escrow account for Damac City?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Cavalli CoutureNearby in Dubai Water Canal. 20%, Due May 2025, passed.
- One CanalNearby in Dubai Water Canal. 77%.
- Casa CanalNearby in Dubai Water Canal. 38%.
- The MelgranoNearby in Dubai Water Canal. 32%, Due December 2026.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.








.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)







.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)