The Rings construction photos
46 photos taken by Dubai Land Department engineers at 9 site inspections, newest first. The percentage is how much of The Rings was built on the day of each visit.
26 August 202635% built
8 June 202629% built
25 March 202624% built
11 December 202521% built
28 July 202512% built
15 May 20258.7% built
22 January 20256.6% built
21 May 20242.7% built
21 September 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.