The Melgrano construction progress

The Melgrano in Dubai Water Canal is 32% built at the Land Department inspection of June 2026. Developer The Melgrano Real Estate Development. Completion registered for December 2026.

32%

Built, at the Land Department site inspection of 18 June 2026

Running behind its date

Completion date (Land Department)
December 2026
Finish at recent pace
June 2028
Construction started
November 2024
Registered with the Land Department
November 2024
Developer
The Melgrano Real Estate Development
Units
14
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
دي ميلجرانو
Land Department project number
2759
Land Department site inspections
7

Schedule

Between September 2025 and June 2026 the site added about 2.9 points a month. At that rate it would finish around June 2028, more than three months after the December 2026 date registered with the Land Department.

0%25%50%75%100%202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

18 June 2026

32%+12 pts

  • The Melgrano construction site, Land Department inspection photo 1, 18 June 2026
  • The Melgrano construction site, Land Department inspection photo 2, 18 June 2026
  • The Melgrano construction site, Land Department inspection photo 3, 18 June 2026
  • The Melgrano construction site, Land Department inspection photo 4, 18 June 2026

23 March 2026

20%+7.5 pts

  • The Melgrano construction site, Land Department inspection photo 1, 23 March 2026
  • The Melgrano construction site, Land Department inspection photo 2, 23 March 2026
  • The Melgrano construction site, Land Department inspection photo 3, 23 March 2026
  • The Melgrano construction site, Land Department inspection photo 4, 23 March 2026

10 December 2025

13%+6.5 pts

  • The Melgrano construction site, Land Department inspection photo 1, 10 December 2025
  • The Melgrano construction site, Land Department inspection photo 2, 10 December 2025
  • The Melgrano construction site, Land Department inspection photo 3, 10 December 2025
  • The Melgrano construction site, Land Department inspection photo 4, 10 December 2025

16 September 2025

6.1%+2.8 pts

  • The Melgrano construction site, Land Department inspection photo 1, 16 September 2025
  • The Melgrano construction site, Land Department inspection photo 2, 16 September 2025
  • The Melgrano construction site, Land Department inspection photo 3, 16 September 2025
  • The Melgrano construction site, Land Department inspection photo 4, 16 September 2025

28 May 2025

3.3%+3.3 pts

  • The Melgrano construction site, Land Department inspection photo 1, 28 May 2025
  • The Melgrano construction site, Land Department inspection photo 2, 28 May 2025
  • The Melgrano construction site, Land Department inspection photo 3, 28 May 2025

27 June 2024

0%

  • The Melgrano construction site, Land Department inspection photo 1, 27 June 2024
  • The Melgrano construction site, Land Department inspection photo 2, 27 June 2024

26 October 2023

0%

  • The Melgrano construction site, Land Department inspection photo 1, 26 October 2023
  • The Melgrano construction site, Land Department inspection photo 2, 26 October 2023

All 30 site photos, by inspection date

Context

Dubai Water Canal has 10 projects under construction, 37% built on average.

Own a unit in The Melgrano?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will The Melgrano be completed?
The completion date registered with the Dubai Land Department is December 2026. At the pace of its recent inspections the site would reach 100% around June 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Melgrano is built?
32%, measured at the Land Department site inspection on 18 June 2026. The Land Department engineers have inspected the site 7 times since October 2023.
Is The Melgrano delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building The Melgrano?
The registered developer is The Melgrano Real Estate Development.
Which bank holds the escrow account for The Melgrano?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.