The Melgrano construction progress

The registered completion date for The Melgrano in Dubai Water Canal is December 2026. At the last site inspection, in October 2026, it was 43% built. The developer is The Melgrano Real Estate Development.

43%

Built, at the site inspection of 12 October 2026

Running behind its date

Registered completion date
December 2026
Finish at recent pace
May 2028
Construction started
November 2024
First registered
November 2024
Developer
The Melgrano Real Estate Development
Units
14
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
دي ميلجرانو
Project number
2759
Site inspections
8

Schedule

Between December 2025 and October 2026 the site added about 3.0 points a month. At that rate it would finish around May 2028, more than three months after its registered date of December 2026.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

12 October 2026

43%+11 pts

  • The Melgrano construction site, inspection photo 1, 12 October 2026
  • The Melgrano construction site, inspection photo 2, 12 October 2026
  • The Melgrano construction site, inspection photo 3, 12 October 2026
  • The Melgrano construction site, inspection photo 4, 12 October 2026

18 June 2026

32%+12 pts

  • The Melgrano construction site, inspection photo 1, 18 June 2026
  • The Melgrano construction site, inspection photo 2, 18 June 2026
  • The Melgrano construction site, inspection photo 3, 18 June 2026
  • The Melgrano construction site, inspection photo 4, 18 June 2026

23 March 2026

20%+7.5 pts

  • The Melgrano construction site, inspection photo 1, 23 March 2026
  • The Melgrano construction site, inspection photo 2, 23 March 2026
  • The Melgrano construction site, inspection photo 3, 23 March 2026
  • The Melgrano construction site, inspection photo 4, 23 March 2026

10 December 2025

13%+6.5 pts

  • The Melgrano construction site, inspection photo 1, 10 December 2025
  • The Melgrano construction site, inspection photo 2, 10 December 2025
  • The Melgrano construction site, inspection photo 3, 10 December 2025
  • The Melgrano construction site, inspection photo 4, 10 December 2025

16 September 2025

6.1%+2.8 pts

  • The Melgrano construction site, inspection photo 1, 16 September 2025
  • The Melgrano construction site, inspection photo 2, 16 September 2025
  • The Melgrano construction site, inspection photo 3, 16 September 2025
  • The Melgrano construction site, inspection photo 4, 16 September 2025

28 May 2025

3.3%+3.3 pts

  • The Melgrano construction site, inspection photo 1, 28 May 2025
  • The Melgrano construction site, inspection photo 2, 28 May 2025
  • The Melgrano construction site, inspection photo 3, 28 May 2025

27 June 2024

0%

  • The Melgrano construction site, inspection photo 1, 27 June 2024
  • The Melgrano construction site, inspection photo 2, 27 June 2024

26 October 2023

0%

  • The Melgrano construction site, inspection photo 1, 26 October 2023
  • The Melgrano construction site, inspection photo 2, 26 October 2023

All 41 site photos, by inspection date

Context

Dubai Water Canal has 11 projects under construction, 38% built on average.

Own a unit in The Melgrano?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Melgrano handover date?
The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Melgrano?
The Melgrano was 43% built at the site inspection on 12 October 2026. The site has been inspected 8 times since October 2023. The Land Department took 41 site photos at its inspections.
Is The Melgrano delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
Who is building The Melgrano?
The registered developer is The Melgrano Real Estate Development.
Which bank holds the escrow account for The Melgrano?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.