The Melgrano construction progress
The registered completion date for The Melgrano in Dubai Water Canal is December 2026. At the last site inspection, in October 2026, it was 43% built. The developer is The Melgrano Real Estate Development.
43%
Built, at the site inspection of 12 October 2026
Running behind its date
- Registered completion date
- December 2026
- Finish at recent pace
- May 2028
- Construction started
- November 2024
- First registered
- November 2024
- Developer
- The Melgrano Real Estate Development
- Community
- Dubai Water Canal
- Units
- 14
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- دي ميلجرانو
- Project number
- 2759
- Site inspections
- 8
Schedule
Between December 2025 and October 2026 the site added about 3.0 points a month. At that rate it would finish around May 2028, more than three months after its registered date of December 2026.
Site inspections
12 October 2026
43%+11 pts
18 June 2026
32%+12 pts
23 March 2026
20%+7.5 pts
10 December 2025
13%+6.5 pts
16 September 2025
6.1%+2.8 pts
28 May 2025
3.3%+3.3 pts
27 June 2024
0%
26 October 2023
0%
Context
Dubai Water Canal has 11 projects under construction, 38% built on average.
Own a unit in The Melgrano?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the The Melgrano handover date?
- The registered completion date is December 2026. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on The Melgrano?
- The Melgrano was 43% built at the site inspection on 12 October 2026. The site has been inspected 8 times since October 2023. The Land Department took 41 site photos at its inspections.
- Is The Melgrano delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2026.
- Who is building The Melgrano?
- The registered developer is The Melgrano Real Estate Development.
- Which bank holds the escrow account for The Melgrano?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Damac CityNearby in Dubai Water Canal. 73%, Due December 2025, passed.
- Cavalli CoutureNearby in Dubai Water Canal. 28%, Due May 2025, passed.
- One CanalNearby in Dubai Water Canal. 88%, Due May 2025, passed.
- Casa CanalNearby in Dubai Water Canal. 43%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)



.jpeg&w=3840&q=75)



.jpeg&w=3840&q=75)