The Melgrano construction photos

30 photos taken by Dubai Land Department engineers at 7 site inspections, newest first. The percentage is how much of The Melgrano was built on the day of each visit.

18 June 202632% built

23 March 202620% built

10 December 202513% built

16 September 20256.1% built

28 May 20253.3% built

27 June 20240% built

26 October 20230% built

Back to The Melgrano construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.