One Canal construction photos

91 photos from 14 site inspections, newest first. The percentage is how much of One Canal was built on the day of each visit.

23 October 202688% built

28 July 202677% built

14 April 202669% built

11 February 202663% built

5 December 202558% built

21 August 202544% built

14 May 202534% built

19 December 202423% built

8 October 202419% built

19 August 202415% built

13 May 20248.8% built

11 December 20237.0% built

24 July 20232.3% built

1 November 20220% built

Back to One Canal construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.