46 photos from 10 site inspections, newest first. The percentage is how much of Cavalli Couture was built on the day of each visit.

4 November 202628% built

8 April 202620% built

23 December 202515% built

30 May 202511% built

5 July 20245.9% built

29 May 20243.6% built

15 November 20233.3% built

4 July 20232.3% built

11 April 20230.7% built

15 September 20220% built

Back to Cavalli Couture construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.