Casa Canal construction photos

50 photos from 9 site inspections, newest first. The percentage is how much of Casa Canal was built on the day of each visit.

28 October 202643% built

17 September 202638% built

24 June 202631% built

18 March 202621% built

7 January 202617% built

15 May 202512% built

10 October 20247.4% built

11 June 20241.7% built

9 June 20230% built

Back to Casa Canal construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.