Canal Front Residences-Cf7 & Cf8 & Cf9 construction progress

The register lists Canal Front Residences-Cf7 & Cf8 & Cf9 in Dubai Water Canal as complete, with a registered completion date of December 2024. Its last site inspection on record was in January 2025. The developer is Meydan Group.

100%

Built, at the site inspection of 3 January 2025

Construction complete

Registered completion date
December 2024
Construction started
May 2018
First registered
March 2022
Developer
Meydan Group
Units
374
Escrow bank
Emirates NBD
Name in Arabic
Cf7&Cf8&Cf9-قنال فرونت ريزيدنسز
Project number
2363
Site inspections
9

Schedule

The register lists Canal Front Residences-Cf7 & Cf8 & Cf9 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2019202120232025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

3 January 2025

100%+8.5 pts

  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 1, 3 January 2025
  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 2, 3 January 2025
  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 3, 3 January 2025
  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 4, 3 January 2025

4 June 2024

91%+15 pts

  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 1, 4 June 2024
  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 2, 4 June 2024
  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 3, 4 June 2024
  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 4, 4 June 2024

4 March 2024

77%+19 pts

  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 1, 4 March 2024
  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 2, 4 March 2024
  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 3, 4 March 2024
  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 4, 4 March 2024

28 August 2023

58%+11 pts

  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 1, 28 August 2023
  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 2, 28 August 2023
  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 3, 28 August 2023
  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 4, 28 August 2023

18 May 2023

47%+6.8 pts

  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 1, 18 May 2023
  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 2, 18 May 2023
  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 3, 18 May 2023
  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 4, 18 May 2023

2 February 2023

40%+3.8 pts

  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 1, 2 February 2023
  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 2, 2 February 2023
  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 3, 2 February 2023
  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 4, 2 February 2023

10 November 2022

37%+3.4 pts

  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 1, 10 November 2022
  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 2, 10 November 2022
  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 3, 10 November 2022
  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 4, 10 November 2022

3 August 2022

33%

  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 1, 3 August 2022
  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 2, 3 August 2022
  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 3, 3 August 2022
  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 4, 3 August 2022

21 February 2022

33%

  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 1, 21 February 2022
  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 2, 21 February 2022
  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 3, 21 February 2022
  • Canal Front Residences-Cf7 & Cf8 & Cf9 construction site, inspection photo 4, 21 February 2022

All 82 site photos, by inspection date

Context

Dubai Water Canal has 11 projects under construction, 38% built on average.

Meydan Group has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Canal Front Residences-Cf7 & Cf8 & Cf9?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Canal Front Residences-Cf7 & Cf8 & Cf9 handover date?
Construction of Canal Front Residences-Cf7 & Cf8 & Cf9 is recorded as complete, with a registered completion date of December 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Canal Front Residences-Cf7 & Cf8 & Cf9?
Canal Front Residences-Cf7 & Cf8 & Cf9 was 100% built at the site inspection on 3 January 2025. The site has been inspected 9 times since February 2022. The Land Department took 82 site photos at its inspections.
Is Canal Front Residences-Cf7 & Cf8 & Cf9 delayed?
The register lists construction as complete.
Who is building Canal Front Residences-Cf7 & Cf8 & Cf9?
The registered developer is Meydan Group. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Canal Front Residences-Cf7 & Cf8 & Cf9?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.