Mohammed Bin Rashid Al Maktoum City -District One West - Phase 2 construction progress
The registered completion date for Mohammed Bin Rashid Al Maktoum City -District One West - Phase 2 in Ghadeer Al Tair is November 2027. At the last site inspection, in October 2026, it was 51% built. The developer is Meydan Group.
51%
Built, at the site inspection of 15 October 2026
On pace for its date
- Registered completion date
- November 2027
- Finish at recent pace
- November 2027
- Construction started
- November 2024
- First registered
- October 2024
- Developer
- Meydan Group
- Community
- Ghadeer Al Tair
- Units
- 229
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- مدينة محمد بن راشد آل مكتوم الحي الأول غرب - المرحلة الثانية
- Project number
- 3200
- Site inspections
- 8
Schedule
Since October 2025 Mohammed Bin Rashid Al Maktoum City -District One West - Phase 2 has added about 3.7 points a month. That puts 100% around November 2027, within three months of its registered completion date of November 2027.
Site inspections
15 October 2026
51%+10 pts
14 July 2026
41%+9.7 pts
17 April 2026
31%+9.4 pts
22 January 2026
22%+15 pts
16 October 2025
7.3%+2.0 pts
25 July 2025
5.3%+3.6 pts
25 April 2025
1.7%+1.7 pts
31 July 2024
0%
Context
Ghadeer Al Tair has 2 projects under construction, 72% built on average.
Meydan Group has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Mohammed Bin Rashid Al Maktoum City -District One West - Phase 2?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Mohammed Bin Rashid Al Maktoum City -District One West - Phase 2 handover date?
- The registered completion date is November 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Mohammed Bin Rashid Al Maktoum City -District One West - Phase 2?
- Mohammed Bin Rashid Al Maktoum City -District One West - Phase 2 was 51% built at the site inspection on 15 October 2026. The site has been inspected 8 times since July 2024. The Land Department took 74 site photos at its inspections.
- Is Mohammed Bin Rashid Al Maktoum City -District One West - Phase 2 delayed?
- Not on current figures. At the rate of the last year it finishes within three months of its registered date of November 2027.
- Who is building Mohammed Bin Rashid Al Maktoum City -District One West - Phase 2?
- The registered developer is Meydan Group. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Mohammed Bin Rashid Al Maktoum City -District One West - Phase 2?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Mohammed Bin Rashid Al Maktoum City District One West - Phase 1Also by Meydan Group. 93%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.





.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)



.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)