Zenith Tower A2 construction progress

The register lists Zenith Tower A2 in Dubai Sports City as complete, with a registered completion date of August 2016. Its last site inspection on record was in October 2017. The developer is Zenith Smart Real Estate Development.

100%

Built, at the site inspection of 1 October 2017

Construction complete

Registered completion date
August 2016
Construction started
October 2013
First registered
December 2014
Developer
Zenith Smart Real Estate Development
Units
161
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
برج زينيث A2
Project number
923
Site inspections
4

Schedule

The register lists Zenith Tower A2 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2014201520162017
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

1 October 2017

100%+5.7 pts

  • Zenith Tower A2 construction site, inspection photo 1, 1 October 2017
  • Zenith Tower A2 construction site, inspection photo 2, 1 October 2017
  • Zenith Tower A2 construction site, inspection photo 3, 1 October 2017
  • Zenith Tower A2 construction site, inspection photo 4, 1 October 2017

1 August 2017

94%+34 pts

  • Zenith Tower A2 construction site, inspection photo 1, 1 August 2017
  • Zenith Tower A2 construction site, inspection photo 2, 1 August 2017
  • Zenith Tower A2 construction site, inspection photo 3, 1 August 2017
  • Zenith Tower A2 construction site, inspection photo 4, 1 August 2017

1 February 2016

60%+18 pts

  • Zenith Tower A2 construction site, inspection photo 1, 1 February 2016
  • Zenith Tower A2 construction site, inspection photo 2, 1 February 2016
  • Zenith Tower A2 construction site, inspection photo 3, 1 February 2016
  • Zenith Tower A2 construction site, inspection photo 4, 1 February 2016

26 March 2015

43%

  • Zenith Tower A2 construction site, inspection photo 1, 26 March 2015
  • Zenith Tower A2 construction site, inspection photo 2, 26 March 2015
  • Zenith Tower A2 construction site, inspection photo 3, 26 March 2015
  • Zenith Tower A2 construction site, inspection photo 4, 26 March 2015

All 26 site photos, by inspection date

Context

Dubai Sports City has 21 projects under construction, 46% built on average.

Own a unit in Zenith Tower A2?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Zenith Tower A2 handover date?
Construction of Zenith Tower A2 is recorded as complete, with a registered completion date of August 2016. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Zenith Tower A2?
Zenith Tower A2 was 100% built at the site inspection on 1 October 2017. The site has been inspected 4 times since March 2015. The Land Department took 26 site photos at its inspections.
Is Zenith Tower A2 delayed?
The register lists construction as complete.
Who is building Zenith Tower A2?
The registered developer is Zenith Smart Real Estate Development.
Which bank holds the escrow account for Zenith Tower A2?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.