The Matrix construction progress

The register lists The Matrix in Dubai Sports City as complete, with a registered completion date of May 2014. Its last site inspection on record was in May 2013. The developer is T F G Real Estate.

100%

Built, at the site inspection of 27 May 2013

Construction complete

Registered completion date
May 2014
Construction started
November 2008
First registered
January 2010
Developer
T F G Real Estate
Units
384
Escrow bank
Mashreq Bank
Name in Arabic
ذا ماتركيس
Project number
99
Site inspections
3

Schedule

The register lists The Matrix as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%200920112013
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

27 May 2013

93%+8.4 pts

  • The Matrix construction site, inspection photo 1, 27 May 2013
  • The Matrix construction site, inspection photo 2, 27 May 2013
  • The Matrix construction site, inspection photo 3, 27 May 2013
  • The Matrix construction site, inspection photo 4, 27 May 2013

20 January 2013

84%+16 pts

  • The Matrix construction site, inspection photo 1, 20 January 2013
  • The Matrix construction site, inspection photo 2, 20 January 2013
  • The Matrix construction site, inspection photo 3, 20 January 2013
  • The Matrix construction site, inspection photo 4, 20 January 2013

1 December 2012

69%

  • The Matrix construction site, inspection photo 1, 1 December 2012
  • The Matrix construction site, inspection photo 2, 1 December 2012
  • The Matrix construction site, inspection photo 3, 1 December 2012
  • The Matrix construction site, inspection photo 4, 1 December 2012

All 28 site photos, by inspection date

Context

Dubai Sports City has 21 projects under construction, 46% built on average.

Own a unit in The Matrix?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the The Matrix handover date?
Construction of The Matrix is recorded as complete, with a registered completion date of May 2014. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on The Matrix?
The Matrix was 100% built at the site inspection on 27 May 2013. The site has been inspected 3 times since December 2012. The Land Department took 28 site photos at its inspections.
Is The Matrix delayed?
The register lists construction as complete.
Who is building The Matrix?
The registered developer is T F G Real Estate.
Which bank holds the escrow account for The Matrix?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.