Red Residence construction progress

The register lists Red Residence in Dubai Sports City as complete, with a registered completion date of November 2015. Its last site inspection on record was in February 2017. The developer is M E Development.

100%

Built, at the site inspection of 5 February 2017

Construction complete

Registered completion date
November 2015
Construction started
June 2009
First registered
November 2008
Developer
M E Development
Units
334
Escrow bank
Al Masraf
Name in Arabic
ريد ريزيدنس
Project number
848
Site inspections
6

Schedule

The register lists Red Residence as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2010201220142016
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

5 February 2017

100%+2.0 pts

  • Red Residence construction site, inspection photo 1, 5 February 2017
  • Red Residence construction site, inspection photo 2, 5 February 2017
  • Red Residence construction site, inspection photo 3, 5 February 2017
  • Red Residence construction site, inspection photo 4, 5 February 2017

2 June 2016

98%+0.2 pts

  • Red Residence construction site, inspection photo 1, 2 June 2016
  • Red Residence construction site, inspection photo 2, 2 June 2016
  • Red Residence construction site, inspection photo 3, 2 June 2016
  • Red Residence construction site, inspection photo 4, 2 June 2016

22 October 2015

98%+5.6 pts

  • Red Residence construction site, inspection photo 1, 22 October 2015
  • Red Residence construction site, inspection photo 2, 22 October 2015
  • Red Residence construction site, inspection photo 3, 22 October 2015
  • Red Residence construction site, inspection photo 4, 22 October 2015

6 May 2014

92%+8.0 pts

  • Red Residence construction site, inspection photo 1, 6 May 2014
  • Red Residence construction site, inspection photo 2, 6 May 2014
  • Red Residence construction site, inspection photo 3, 6 May 2014
  • Red Residence construction site, inspection photo 4, 6 May 2014

8 December 2013

84%+4.2 pts

  • Red Residence construction site, inspection photo 1, 8 December 2013
  • Red Residence construction site, inspection photo 2, 8 December 2013
  • Red Residence construction site, inspection photo 3, 8 December 2013
  • Red Residence construction site, inspection photo 4, 8 December 2013

17 July 2013

80%

  • Red Residence construction site, inspection photo 1, 17 July 2013
  • Red Residence construction site, inspection photo 2, 17 July 2013
  • Red Residence construction site, inspection photo 3, 17 July 2013
  • Red Residence construction site, inspection photo 4, 17 July 2013

All 62 site photos, by inspection date

Context

Dubai Sports City has 21 projects under construction, 46% built on average.

Own a unit in Red Residence?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Red Residence handover date?
Construction of Red Residence is recorded as complete, with a registered completion date of November 2015. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Red Residence?
Red Residence was 100% built at the site inspection on 5 February 2017. The site has been inspected 6 times since July 2013. The Land Department took 62 site photos at its inspections.
Is Red Residence delayed?
The register lists construction as complete.
Who is building Red Residence?
The registered developer is M E Development.
Which bank holds the escrow account for Red Residence?
Al Masraf. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.