Prime Villas construction progress
The register lists Prime Villas in Dubai Sports City as complete, with a registered completion date of October 2016. Its last site inspection on record was in February 2017. The developer is Prescott Developers Limited.
100%
Built, at the site inspection of 21 February 2017
Construction complete
- Registered completion date
- October 2016
- Construction started
- September 2013
- First registered
- August 2013
- Developer
- Prescott Developers Limited
- Community
- Dubai Sports City
- Units
- 32
- Escrow bank
- Mashreq Bank
- Name in Arabic
- برايم فيلا
- Project number
- 1367
- Site inspections
- 5
Schedule
The register lists Prime Villas as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
21 February 2017
100%+12 pts
4 September 2016
88%+33 pts
7 January 2016
55%+30 pts
30 March 2015
24%+21 pts
12 May 2014
2.8%
Context
Dubai Sports City has 21 projects under construction, 46% built on average.
Own a unit in Prime Villas?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Prime Villas handover date?
- Construction of Prime Villas is recorded as complete, with a registered completion date of October 2016. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Prime Villas?
- Prime Villas was 100% built at the site inspection on 21 February 2017. The site has been inspected 5 times since May 2014. The Land Department took 49 site photos at its inspections.
- Is Prime Villas delayed?
- The register lists construction as complete.
- Who is building Prime Villas?
- The registered developer is Prescott Developers Limited.
- Which bank holds the escrow account for Prime Villas?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Eden GardenNearby in Dubai Sports City. 96%, Due August 2022, passed.
- Mars ResidencesNearby in Dubai Sports City. 80%, Due March 2024, passed.
- Lime Light Twin TowersNearby in Dubai Sports City. 71%, Due June 2026, passed.
- Azizi GrandNearby in Dubai Sports City. 82%, Due February 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.