Hera Tower construction progress

The register lists Hera Tower in Dubai Sports City as complete, with a registered completion date of February 2022. Its last site inspection on record was in February 2022. The developer is Titans Real Estate Developers.

100%

Built, at the site inspection of 7 February 2022

Construction complete

Registered completion date
February 2022
Construction started
December 2015
First registered
August 2015
Developer
Titans Real Estate Developers
Units
531
Escrow bank
Commercial Bank International
Name in Arabic
هيرا تاور
Project number
336
Site inspections
14

Schedule

The register lists Hera Tower as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2016201820202022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

7 February 2022

100%+7.9 pts

  • Hera Tower construction site, inspection photo 1, 7 February 2022
  • Hera Tower construction site, inspection photo 2, 7 February 2022
  • Hera Tower construction site, inspection photo 3, 7 February 2022
  • Hera Tower construction site, inspection photo 4, 7 February 2022

15 July 2021

92%+6.0 pts

  • Hera Tower construction site, inspection photo 1, 15 July 2021
  • Hera Tower construction site, inspection photo 2, 15 July 2021
  • Hera Tower construction site, inspection photo 3, 15 July 2021
  • Hera Tower construction site, inspection photo 4, 15 July 2021

14 April 2021

86%+6.0 pts

  • Hera Tower construction site, inspection photo 1, 14 April 2021
  • Hera Tower construction site, inspection photo 2, 14 April 2021
  • Hera Tower construction site, inspection photo 3, 14 April 2021
  • Hera Tower construction site, inspection photo 4, 14 April 2021

7 December 2020

80%+4.5 pts

  • Hera Tower construction site, inspection photo 1, 7 December 2020
  • Hera Tower construction site, inspection photo 2, 7 December 2020
  • Hera Tower construction site, inspection photo 3, 7 December 2020
  • Hera Tower construction site, inspection photo 4, 7 December 2020

2 March 2020

75%+5.5 pts

  • Hera Tower construction site, inspection photo 1, 2 March 2020
  • Hera Tower construction site, inspection photo 2, 2 March 2020
  • Hera Tower construction site, inspection photo 3, 2 March 2020
  • Hera Tower construction site, inspection photo 4, 2 March 2020

19 September 2019

70%+10.0 pts

  • Hera Tower construction site, inspection photo 1, 19 September 2019
  • Hera Tower construction site, inspection photo 2, 19 September 2019
  • Hera Tower construction site, inspection photo 3, 19 September 2019
  • Hera Tower construction site, inspection photo 4, 19 September 2019

21 January 2019

60%+19 pts

  • Hera Tower construction site, inspection photo 1, 21 January 2019
  • Hera Tower construction site, inspection photo 2, 21 January 2019
  • Hera Tower construction site, inspection photo 3, 21 January 2019
  • Hera Tower construction site, inspection photo 4, 21 January 2019

20 September 2018

41%+10 pts

  • Hera Tower construction site, inspection photo 1, 20 September 2018
  • Hera Tower construction site, inspection photo 2, 20 September 2018
  • Hera Tower construction site, inspection photo 3, 20 September 2018
  • Hera Tower construction site, inspection photo 4, 20 September 2018

18 June 2018

31%+9.8 pts

  • Hera Tower construction site, inspection photo 1, 18 June 2018
  • Hera Tower construction site, inspection photo 2, 18 June 2018
  • Hera Tower construction site, inspection photo 3, 18 June 2018
  • Hera Tower construction site, inspection photo 4, 18 June 2018

8 February 2018

21%+6.2 pts

  • Hera Tower construction site, inspection photo 1, 8 February 2018
  • Hera Tower construction site, inspection photo 2, 8 February 2018
  • Hera Tower construction site, inspection photo 3, 8 February 2018
  • Hera Tower construction site, inspection photo 4, 8 February 2018

All 127 site photos, by inspection date

Context

Dubai Sports City has 21 projects under construction, 46% built on average.

Own a unit in Hera Tower?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Hera Tower handover date?
Construction of Hera Tower is recorded as complete, with a registered completion date of February 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Hera Tower?
Hera Tower was 100% built at the site inspection on 7 February 2022. The site has been inspected 14 times since August 2016. The Land Department took 127 site photos at its inspections.
Is Hera Tower delayed?
The register lists construction as complete.
Who is building Hera Tower?
The registered developer is Titans Real Estate Developers.
Which bank holds the escrow account for Hera Tower?
Commercial Bank International. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.