Frankfurt Sports Tower I construction progress

The register lists Frankfurt Sports Tower I in Dubai Sports City as complete, with a registered completion date of January 2016. Its last site inspection on record was in March 2016. The developer is Sumsum Developers Limited.

100%

Built, at the site inspection of 23 March 2016

Construction complete

Registered completion date
January 2016
Construction started
January 2009
First registered
November 2008
Developer
Sumsum Developers Limited
Units
224
Escrow bank
Commercial Bank of Dubai
Name in Arabic
برج فرانكفورت الرياضي 1
Project number
315
Site inspections
7

Schedule

The register lists Frankfurt Sports Tower I as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2010201220142016
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

23 March 2016

100%+1.0 pts

  • Frankfurt Sports Tower I construction site, inspection photo 1, 23 March 2016
  • Frankfurt Sports Tower I construction site, inspection photo 2, 23 March 2016
  • Frankfurt Sports Tower I construction site, inspection photo 3, 23 March 2016
  • Frankfurt Sports Tower I construction site, inspection photo 4, 23 March 2016

18 February 2016

99%+7.6 pts

  • Frankfurt Sports Tower I construction site, inspection photo 1, 18 February 2016
  • Frankfurt Sports Tower I construction site, inspection photo 2, 18 February 2016
  • Frankfurt Sports Tower I construction site, inspection photo 3, 18 February 2016
  • Frankfurt Sports Tower I construction site, inspection photo 4, 18 February 2016

16 February 2015

91%+21 pts

  • Frankfurt Sports Tower I construction site, inspection photo 1, 16 February 2015
  • Frankfurt Sports Tower I construction site, inspection photo 2, 16 February 2015
  • Frankfurt Sports Tower I construction site, inspection photo 3, 16 February 2015
  • Frankfurt Sports Tower I construction site, inspection photo 4, 16 February 2015

8 October 2014

71%+16 pts

  • Frankfurt Sports Tower I construction site, inspection photo 1, 8 October 2014
  • Frankfurt Sports Tower I construction site, inspection photo 2, 8 October 2014
  • Frankfurt Sports Tower I construction site, inspection photo 3, 8 October 2014
  • Frankfurt Sports Tower I construction site, inspection photo 4, 8 October 2014

9 April 2014

55%+7.8 pts

  • Frankfurt Sports Tower I construction site, inspection photo 1, 9 April 2014
  • Frankfurt Sports Tower I construction site, inspection photo 2, 9 April 2014
  • Frankfurt Sports Tower I construction site, inspection photo 3, 9 April 2014
  • Frankfurt Sports Tower I construction site, inspection photo 4, 9 April 2014

28 November 2013

47%+6.9 pts

  • Frankfurt Sports Tower I construction site, inspection photo 1, 28 November 2013
  • Frankfurt Sports Tower I construction site, inspection photo 2, 28 November 2013
  • Frankfurt Sports Tower I construction site, inspection photo 3, 28 November 2013
  • Frankfurt Sports Tower I construction site, inspection photo 4, 28 November 2013

18 June 2013

40%

  • Frankfurt Sports Tower I construction site, inspection photo 1, 18 June 2013
  • Frankfurt Sports Tower I construction site, inspection photo 2, 18 June 2013
  • Frankfurt Sports Tower I construction site, inspection photo 3, 18 June 2013
  • Frankfurt Sports Tower I construction site, inspection photo 4, 18 June 2013

All 76 site photos, by inspection date

Context

Dubai Sports City has 21 projects under construction, 46% built on average.

Own a unit in Frankfurt Sports Tower I?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Frankfurt Sports Tower I handover date?
Construction of Frankfurt Sports Tower I is recorded as complete, with a registered completion date of January 2016. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Frankfurt Sports Tower I?
Frankfurt Sports Tower I was 100% built at the site inspection on 23 March 2016. The site has been inspected 7 times since June 2013. The Land Department took 76 site photos at its inspections.
Is Frankfurt Sports Tower I delayed?
The register lists construction as complete.
Who is building Frankfurt Sports Tower I?
The registered developer is Sumsum Developers Limited.
Which bank holds the escrow account for Frankfurt Sports Tower I?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.