Cricket Tower construction progress

The register lists Cricket Tower in Dubai Sports City as complete, with a registered completion date of September 2016. Its last site inspection on record was in December 2016. The developer is Falak Properties.

100%

Built, at the site inspection of 25 December 2016

Construction complete

Registered completion date
September 2016
Construction started
May 2007
First registered
November 2010
Developer
Falak Properties
Units
168
Name in Arabic
برج الكريكيت
Project number
1299
Site inspections
4

Schedule

The register lists Cricket Tower as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20082010201220142016
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

25 December 2016

100%+0.8 pts

  • Cricket Tower construction site, inspection photo 1, 25 December 2016
  • Cricket Tower construction site, inspection photo 2, 25 December 2016
  • Cricket Tower construction site, inspection photo 3, 25 December 2016
  • Cricket Tower construction site, inspection photo 4, 25 December 2016

28 September 2016

99%+2.8 pts

  • Cricket Tower construction site, inspection photo 1, 28 September 2016
  • Cricket Tower construction site, inspection photo 2, 28 September 2016
  • Cricket Tower construction site, inspection photo 3, 28 September 2016
  • Cricket Tower construction site, inspection photo 4, 28 September 2016

18 May 2015

96%+7.0 pts

  • Cricket Tower construction site, inspection photo 1, 18 May 2015
  • Cricket Tower construction site, inspection photo 2, 18 May 2015
  • Cricket Tower construction site, inspection photo 3, 18 May 2015

10 June 2014

89%

  • Cricket Tower construction site, inspection photo 1, 10 June 2014
  • Cricket Tower construction site, inspection photo 2, 10 June 2014
  • Cricket Tower construction site, inspection photo 3, 10 June 2014
  • Cricket Tower construction site, inspection photo 4, 10 June 2014

All 38 site photos, by inspection date

Context

Dubai Sports City has 21 projects under construction, 46% built on average.

Own a unit in Cricket Tower?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Cricket Tower handover date?
Construction of Cricket Tower is recorded as complete, with a registered completion date of September 2016. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Cricket Tower?
Cricket Tower was 100% built at the site inspection on 25 December 2016. The site has been inspected 4 times since June 2014. The Land Department took 38 site photos at its inspections.
Is Cricket Tower delayed?
The register lists construction as complete.
Who is building Cricket Tower?
The registered developer is Falak Properties.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.