Champions Tower1 construction progress

The register lists Champions Tower1 in Dubai Sports City as complete, with a registered completion date of January 2017. Its last site inspection on record was in February 2017. The developer is Mre Global Investment Group.

100%

Built, at the site inspection of 23 February 2017

Construction complete

Registered completion date
January 2017
Construction started
September 2007
First registered
November 2008
Developer
Mre Global Investment Group
Units
135
Escrow bank
Commercial Bank of Dubai
Name in Arabic
شامبيونز تاور 1
Project number
763
Site inspections
6

Schedule

The register lists Champions Tower1 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20082010201220142016
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

23 February 2017

100%+3.5 pts

  • Champions Tower1 construction site, inspection photo 1, 23 February 2017
  • Champions Tower1 construction site, inspection photo 2, 23 February 2017
  • Champions Tower1 construction site, inspection photo 3, 23 February 2017
  • Champions Tower1 construction site, inspection photo 4, 23 February 2017

16 October 2016

97%+1.7 pts

  • Champions Tower1 construction site, inspection photo 1, 16 October 2016
  • Champions Tower1 construction site, inspection photo 2, 16 October 2016
  • Champions Tower1 construction site, inspection photo 3, 16 October 2016
  • Champions Tower1 construction site, inspection photo 4, 16 October 2016

8 October 2015

95%+4.8 pts

  • Champions Tower1 construction site, inspection photo 1, 8 October 2015
  • Champions Tower1 construction site, inspection photo 2, 8 October 2015
  • Champions Tower1 construction site, inspection photo 3, 8 October 2015
  • Champions Tower1 construction site, inspection photo 4, 8 October 2015

19 July 2014

90%+6.3 pts

  • Champions Tower1 construction site, inspection photo 1, 19 July 2014
  • Champions Tower1 construction site, inspection photo 2, 19 July 2014
  • Champions Tower1 construction site, inspection photo 3, 19 July 2014
  • Champions Tower1 construction site, inspection photo 4, 19 July 2014

24 November 2013

84%+5.4 pts

  • Champions Tower1 construction site, inspection photo 1, 24 November 2013
  • Champions Tower1 construction site, inspection photo 2, 24 November 2013
  • Champions Tower1 construction site, inspection photo 3, 24 November 2013
  • Champions Tower1 construction site, inspection photo 4, 24 November 2013

24 February 2013

78%

  • Champions Tower1 construction site, inspection photo 1, 24 February 2013
  • Champions Tower1 construction site, inspection photo 2, 24 February 2013
  • Champions Tower1 construction site, inspection photo 3, 24 February 2013
  • Champions Tower1 construction site, inspection photo 4, 24 February 2013

All 79 site photos, by inspection date

Context

Dubai Sports City has 21 projects under construction, 46% built on average.

Own a unit in Champions Tower1?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Champions Tower1 handover date?
Construction of Champions Tower1 is recorded as complete, with a registered completion date of January 2017. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Champions Tower1?
Champions Tower1 was 100% built at the site inspection on 23 February 2017. The site has been inspected 6 times since February 2013. The Land Department took 79 site photos at its inspections.
Is Champions Tower1 delayed?
The register lists construction as complete.
Who is building Champions Tower1?
The registered developer is Mre Global Investment Group.
Which bank holds the escrow account for Champions Tower1?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.