Bermuda Views construction progress

The register lists Bermuda Views in Dubai Sports City as complete, with a registered completion date of September 2015. Its last site inspection on record was in August 2015. The developer is Hma Exec Limited.

100%

Built, at the site inspection of 16 August 2015

Construction complete

Registered completion date
September 2015
Construction started
January 2010
First registered
November 2008
Developer
Hma Exec Limited
Units
236
Escrow bank
Dubai Islamic Bank
Name in Arabic
برمودا فيوز
Project number
616
Site inspections
7

Schedule

The register lists Bermuda Views as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20112012201320142015
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

16 August 2015

95%+18 pts

  • Bermuda Views construction site, inspection photo 1, 16 August 2015
  • Bermuda Views construction site, inspection photo 2, 16 August 2015
  • Bermuda Views construction site, inspection photo 3, 16 August 2015
  • Bermuda Views construction site, inspection photo 4, 16 August 2015

7 April 2015

78%+13 pts

  • Bermuda Views construction site, inspection photo 1, 7 April 2015
  • Bermuda Views construction site, inspection photo 2, 7 April 2015
  • Bermuda Views construction site, inspection photo 3, 7 April 2015
  • Bermuda Views construction site, inspection photo 4, 7 April 2015

27 December 2014

65%+13 pts

  • Bermuda Views construction site, inspection photo 1, 27 December 2014
  • Bermuda Views construction site, inspection photo 2, 27 December 2014
  • Bermuda Views construction site, inspection photo 3, 27 December 2014
  • Bermuda Views construction site, inspection photo 4, 27 December 2014

1 September 2014

52%+12 pts

  • Bermuda Views construction site, inspection photo 1, 1 September 2014
  • Bermuda Views construction site, inspection photo 2, 1 September 2014
  • Bermuda Views construction site, inspection photo 3, 1 September 2014
  • Bermuda Views construction site, inspection photo 4, 1 September 2014

4 March 2014

40%+1.0 pts

  • Bermuda Views construction site, inspection photo 1, 4 March 2014
  • Bermuda Views construction site, inspection photo 2, 4 March 2014
  • Bermuda Views construction site, inspection photo 3, 4 March 2014
  • Bermuda Views construction site, inspection photo 4, 4 March 2014

10 November 2013

39%

  • Bermuda Views construction site, inspection photo 1, 10 November 2013
  • Bermuda Views construction site, inspection photo 2, 10 November 2013
  • Bermuda Views construction site, inspection photo 3, 10 November 2013
  • Bermuda Views construction site, inspection photo 4, 10 November 2013

21 February 2013

39%

  • Bermuda Views construction site, inspection photo 1, 21 February 2013
  • Bermuda Views construction site, inspection photo 2, 21 February 2013
  • Bermuda Views construction site, inspection photo 3, 21 February 2013

All 86 site photos, by inspection date

Context

Dubai Sports City has 21 projects under construction, 46% built on average.

Own a unit in Bermuda Views?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Bermuda Views handover date?
Construction of Bermuda Views is recorded as complete, with a registered completion date of September 2015. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Bermuda Views?
Bermuda Views was 100% built at the site inspection on 16 August 2015. The site has been inspected 7 times since February 2013. The Land Department took 86 site photos at its inspections.
Is Bermuda Views delayed?
The register lists construction as complete.
Who is building Bermuda Views?
The registered developer is Hma Exec Limited.
Which bank holds the escrow account for Bermuda Views?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.