Chelsea Residences By Damac construction progress

Chelsea Residences By Damac in Dubai Maritime City is 5.2% built at the Land Department inspection of August 2026. Developer Damac Crest Development. Completion registered for December 2029.

5.2%

Built, at the Land Department site inspection of 7 August 2026

Running behind its date

Completion date (Land Department)
December 2029
Finish at recent pace
March 2041
Construction started
July 2025
Registered with the Land Department
April 2025
Developer
Damac Crest Development
Units
703
Escrow bank
Dubai Islamic Bank
Name in Arabic
تشيلسي ريزيدنس باي داماك
Land Department project number
3719
Land Department site inspections
4

Schedule

Between October 2025 and August 2026 the site added about 0.5 points a month. At that rate it would finish around March 2041, more than three months after the December 2029 date registered with the Land Department.

0%25%50%75%100%2026202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

7 August 2026

5.2%+4.5 pts

  • Chelsea Residences By Damac construction site, Land Department inspection photo 1, 7 August 2026
  • Chelsea Residences By Damac construction site, Land Department inspection photo 2, 7 August 2026
  • Chelsea Residences By Damac construction site, Land Department inspection photo 3, 7 August 2026
  • Chelsea Residences By Damac construction site, Land Department inspection photo 4, 7 August 2026

9 April 2026

0.7%+0.6 pts

  • Chelsea Residences By Damac construction site, Land Department inspection photo 1, 9 April 2026
  • Chelsea Residences By Damac construction site, Land Department inspection photo 2, 9 April 2026
  • Chelsea Residences By Damac construction site, Land Department inspection photo 3, 9 April 2026
  • Chelsea Residences By Damac construction site, Land Department inspection photo 4, 9 April 2026

23 October 2025

0.1%+0.1 pts

  • Chelsea Residences By Damac construction site, Land Department inspection photo 1, 23 October 2025
  • Chelsea Residences By Damac construction site, Land Department inspection photo 2, 23 October 2025
  • Chelsea Residences By Damac construction site, Land Department inspection photo 3, 23 October 2025

24 April 2025

0%

  • Chelsea Residences By Damac construction site, Land Department inspection photo 1, 24 April 2025
  • Chelsea Residences By Damac construction site, Land Department inspection photo 2, 24 April 2025

All 14 site photos, by inspection date

Context

Dubai Maritime City has 23 projects under construction, 29% built on average.

Damac Crest Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Chelsea Residences By Damac?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Chelsea Residences By Damac be completed?
The completion date registered with the Dubai Land Department is December 2029. At the pace of its recent inspections the site would reach 100% around March 2041. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Chelsea Residences By Damac is built?
5.2%, measured at the Land Department site inspection on 7 August 2026. The Land Department engineers have inspected the site 4 times since April 2025.
Is Chelsea Residences By Damac delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2029.
Who is building Chelsea Residences By Damac?
The registered developer is Damac Crest Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Chelsea Residences By Damac?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.