Chelsea Residences By Damac construction progress

The registered completion date for Chelsea Residences By Damac in Dubai Maritime City is December 2029. At the last site inspection, in November 2026, it was 6.5% built. The developer is Damac Crest Development.

6.5%

Built, at the site inspection of 11 November 2026

Running behind its date

Registered completion date
December 2029
Finish at recent pace
April 2036
Construction started
July 2025
First registered
April 2025
Developer
Damac Crest Development
Units
703
Escrow bank
Dubai Islamic Bank
Name in Arabic
تشيلسي ريزيدنس باي داماك
Project number
3719
Site inspections
5

Schedule

Between April 2026 and November 2026 the site added about 0.8 points a month. At that rate it would finish around April 2036, more than three months after its registered date of December 2029.

0%25%50%75%100%2026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

11 November 2026

6.5%+1.3 pts

  • Chelsea Residences By Damac construction site, inspection photo 1, 11 November 2026
  • Chelsea Residences By Damac construction site, inspection photo 2, 11 November 2026
  • Chelsea Residences By Damac construction site, inspection photo 3, 11 November 2026
  • Chelsea Residences By Damac construction site, inspection photo 4, 11 November 2026

7 August 2026

5.2%+4.5 pts

  • Chelsea Residences By Damac construction site, inspection photo 1, 7 August 2026
  • Chelsea Residences By Damac construction site, inspection photo 2, 7 August 2026
  • Chelsea Residences By Damac construction site, inspection photo 3, 7 August 2026
  • Chelsea Residences By Damac construction site, inspection photo 4, 7 August 2026

9 April 2026

0.7%+0.6 pts

  • Chelsea Residences By Damac construction site, inspection photo 1, 9 April 2026
  • Chelsea Residences By Damac construction site, inspection photo 2, 9 April 2026
  • Chelsea Residences By Damac construction site, inspection photo 3, 9 April 2026
  • Chelsea Residences By Damac construction site, inspection photo 4, 9 April 2026

23 October 2025

0.1%+0.1 pts

  • Chelsea Residences By Damac construction site, inspection photo 1, 23 October 2025
  • Chelsea Residences By Damac construction site, inspection photo 2, 23 October 2025
  • Chelsea Residences By Damac construction site, inspection photo 3, 23 October 2025

24 April 2025

0%

  • Chelsea Residences By Damac construction site, inspection photo 1, 24 April 2025
  • Chelsea Residences By Damac construction site, inspection photo 2, 24 April 2025

All 20 site photos, by inspection date

Context

Dubai Maritime City has 23 projects under construction, 32% built on average.

Damac Crest Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Chelsea Residences By Damac?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Chelsea Residences By Damac handover date?
The registered completion date is December 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2036. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Chelsea Residences By Damac?
Chelsea Residences By Damac was 6.5% built at the site inspection on 11 November 2026. The site has been inspected 5 times since April 2025. The Land Department took 20 site photos at its inspections.
Is Chelsea Residences By Damac delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2029.
Who is building Chelsea Residences By Damac?
The registered developer is Damac Crest Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Chelsea Residences By Damac?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.