Chelsea Residences 2 By Damac construction progress

Chelsea Residences 2 By Damac in Dubai Maritime City is 5.4% built at the Land Department inspection of August 2026. Developer Damac Crest Development. Completion registered for December 2029.

5.4%

Built, at the Land Department site inspection of 6 August 2026

Running behind its date

Completion date (Land Department)
December 2029
Finish at recent pace
September 2039
Construction started
September 2025
Registered with the Land Department
May 2025
Developer
Damac Crest Development
Units
958
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
تشلسي ريزيدنس 2 باي داماك
Land Department project number
3743
Land Department site inspections
4

Schedule

Between November 2025 and August 2026 the site added about 0.6 points a month. At that rate it would finish around September 2039, more than three months after the December 2029 date registered with the Land Department.

0%25%50%75%100%2026202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

6 August 2026

5.4%+4.8 pts

  • Chelsea Residences 2 By Damac construction site, Land Department inspection photo 1, 6 August 2026
  • Chelsea Residences 2 By Damac construction site, Land Department inspection photo 2, 6 August 2026
  • Chelsea Residences 2 By Damac construction site, Land Department inspection photo 3, 6 August 2026
  • Chelsea Residences 2 By Damac construction site, Land Department inspection photo 4, 6 August 2026

9 April 2026

0.7%+0.6 pts

  • Chelsea Residences 2 By Damac construction site, Land Department inspection photo 1, 9 April 2026
  • Chelsea Residences 2 By Damac construction site, Land Department inspection photo 2, 9 April 2026
  • Chelsea Residences 2 By Damac construction site, Land Department inspection photo 3, 9 April 2026
  • Chelsea Residences 2 By Damac construction site, Land Department inspection photo 4, 9 April 2026

5 November 2025

0%+0.0 pts

  • Chelsea Residences 2 By Damac construction site, Land Department inspection photo 1, 5 November 2025
  • Chelsea Residences 2 By Damac construction site, Land Department inspection photo 2, 5 November 2025

5 May 2025

0%

  • Chelsea Residences 2 By Damac construction site, Land Department inspection photo 1, 5 May 2025
  • Chelsea Residences 2 By Damac construction site, Land Department inspection photo 2, 5 May 2025

All 14 site photos, by inspection date

Context

Dubai Maritime City has 23 projects under construction, 29% built on average.

Damac Crest Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Chelsea Residences 2 By Damac?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Chelsea Residences 2 By Damac be completed?
The completion date registered with the Dubai Land Department is December 2029. At the pace of its recent inspections the site would reach 100% around September 2039. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Chelsea Residences 2 By Damac is built?
5.4%, measured at the Land Department site inspection on 6 August 2026. The Land Department engineers have inspected the site 4 times since May 2025.
Is Chelsea Residences 2 By Damac delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2029.
Who is building Chelsea Residences 2 By Damac?
The registered developer is Damac Crest Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Chelsea Residences 2 By Damac?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.