Stella Maris construction progress
The register lists Stella Maris in Dubai Marina as complete, with a registered completion date of June 2022. Its last site inspection on record was in October 2022. The developer is Scope Investment - Dubai Branch.
100%
Built, at the site inspection of 12 October 2022
Construction complete
- Registered completion date
- June 2022
- Construction started
- July 2015
- First registered
- June 2015
- Developer
- Scope Investment - Dubai Branch
- Community
- Dubai Marina
- Units
- 317
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- Stella Maris
- Project number
- 1664
- Site inspections
- 20
Schedule
The register lists Stella Maris as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
12 October 2022
100%+9.5 pts
28 June 2022
90%+9.4 pts
30 March 2022
81%+7.0 pts
27 December 2021
74%+8.8 pts
27 September 2021
65%+8.6 pts
4 July 2021
57%+6.5 pts
1 April 2021
50%+10 pts
20 December 2020
40%+6.7 pts
30 September 2020
33%+7.4 pts
22 June 2020
26%+3.6 pts
Context
Dubai Marina has 13 projects under construction, 46% built on average.
Own a unit in Stella Maris?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Stella Maris handover date?
- Construction of Stella Maris is recorded as complete, with a registered completion date of June 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Stella Maris?
- Stella Maris was 100% built at the site inspection on 12 October 2022. The site has been inspected 20 times since October 2015. The Land Department took 164 site photos at its inspections.
- Is Stella Maris delayed?
- The register lists construction as complete.
- Who is building Stella Maris?
- The registered developer is Scope Investment - Dubai Branch.
- Which bank holds the escrow account for Stella Maris?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Pier 8Nearby in Dubai Marina. 93%, Due March 2026, passed.
- Marina ShoresNearby in Dubai Marina. 87%, Due December 2026.
- Liv LuxNearby in Dubai Marina. 87%, Due December 2026.
- Bluewaters BayNearby in Dubai Marina. 37%, Due March 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.