Marina Wharf II construction progress

The register lists Marina Wharf II in Dubai Marina as complete, with a registered completion date of June 2014. Its last site inspection on record was in June 2014. The developer is Dheeraj & East Coast.

100%

Built, at the site inspection of 25 June 2014

Construction complete

Registered completion date
June 2014
Construction started
July 2007
First registered
November 2008
Developer
Dheeraj & East Coast
Community
Dubai Marina
Units
179
Escrow bank
Bank of Baroda
Name in Arabic
مارينا وارف Ii
Project number
267
Site inspections
5

Schedule

The register lists Marina Wharf II as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2008201020122014
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

25 June 2014

84%+1.8 pts

  • Marina Wharf II construction site, inspection photo 1, 25 June 2014
  • Marina Wharf II construction site, inspection photo 2, 25 June 2014
  • Marina Wharf II construction site, inspection photo 3, 25 June 2014
  • Marina Wharf II construction site, inspection photo 4, 25 June 2014

16 January 2014

82%+13 pts

  • Marina Wharf II construction site, inspection photo 1, 16 January 2014
  • Marina Wharf II construction site, inspection photo 2, 16 January 2014
  • Marina Wharf II construction site, inspection photo 3, 16 January 2014
  • Marina Wharf II construction site, inspection photo 4, 16 January 2014

19 June 2013

69%+7.0 pts

  • Marina Wharf II construction site, inspection photo 1, 19 June 2013
  • Marina Wharf II construction site, inspection photo 2, 19 June 2013
  • Marina Wharf II construction site, inspection photo 3, 19 June 2013
  • Marina Wharf II construction site, inspection photo 4, 19 June 2013

3 October 2012

62%+13 pts

  • Marina Wharf II construction site, inspection photo 1, 3 October 2012
  • Marina Wharf II construction site, inspection photo 2, 3 October 2012
  • Marina Wharf II construction site, inspection photo 3, 3 October 2012
  • Marina Wharf II construction site, inspection photo 4, 3 October 2012

12 June 2012

49%

  • Marina Wharf II construction site, inspection photo 1, 12 June 2012
  • Marina Wharf II construction site, inspection photo 2, 12 June 2012
  • Marina Wharf II construction site, inspection photo 3, 12 June 2012
  • Marina Wharf II construction site, inspection photo 4, 12 June 2012

All 53 site photos, by inspection date

Context

Dubai Marina has 13 projects under construction, 46% built on average.

Own a unit in Marina Wharf II?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Marina Wharf II handover date?
Construction of Marina Wharf II is recorded as complete, with a registered completion date of June 2014. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Marina Wharf II?
Marina Wharf II was 100% built at the site inspection on 25 June 2014. The site has been inspected 5 times since June 2012. The Land Department took 53 site photos at its inspections.
Is Marina Wharf II delayed?
The register lists construction as complete.
Who is building Marina Wharf II?
The registered developer is Dheeraj & East Coast.
Which bank holds the escrow account for Marina Wharf II?
Bank of Baroda. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.