Liv Marina construction progress

The register lists Liv Marina in Dubai Marina as complete, with a registered completion date of May 2025. Its last site inspection on record was in April 2025. The developer is L I V Real Estate Development.

100%

Built, at the site inspection of 17 April 2025

Construction complete

Registered completion date
May 2025
Construction started
June 2021
First registered
February 2022
Developer
L I V Real Estate Development
Community
Dubai Marina
Units
243
Escrow bank
Dubai Islamic Bank
Name in Arabic
ليف مارينا
Project number
2352
Site inspections
8

Schedule

The register lists Liv Marina as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2022202320242025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 April 2025

100%+7.3 pts

  • Liv Marina construction site, inspection photo 1, 17 April 2025
  • Liv Marina construction site, inspection photo 2, 17 April 2025
  • Liv Marina construction site, inspection photo 3, 17 April 2025
  • Liv Marina construction site, inspection photo 4, 17 April 2025

31 October 2024

93%+25 pts

  • Liv Marina construction site, inspection photo 1, 31 October 2024
  • Liv Marina construction site, inspection photo 2, 31 October 2024
  • Liv Marina construction site, inspection photo 3, 31 October 2024
  • Liv Marina construction site, inspection photo 4, 31 October 2024

13 February 2024

67%+11 pts

  • Liv Marina construction site, inspection photo 1, 13 February 2024
  • Liv Marina construction site, inspection photo 2, 13 February 2024
  • Liv Marina construction site, inspection photo 3, 13 February 2024
  • Liv Marina construction site, inspection photo 4, 13 February 2024

25 October 2023

56%+26 pts

  • Liv Marina construction site, inspection photo 1, 25 October 2023
  • Liv Marina construction site, inspection photo 2, 25 October 2023
  • Liv Marina construction site, inspection photo 3, 25 October 2023
  • Liv Marina construction site, inspection photo 4, 25 October 2023

7 March 2023

30%+9.9 pts

  • Liv Marina construction site, inspection photo 1, 7 March 2023
  • Liv Marina construction site, inspection photo 2, 7 March 2023
  • Liv Marina construction site, inspection photo 3, 7 March 2023
  • Liv Marina construction site, inspection photo 4, 7 March 2023

21 November 2022

20%+5.7 pts

  • Liv Marina construction site, inspection photo 1, 21 November 2022
  • Liv Marina construction site, inspection photo 2, 21 November 2022
  • Liv Marina construction site, inspection photo 3, 21 November 2022
  • Liv Marina construction site, inspection photo 4, 21 November 2022

9 August 2022

15%+8.3 pts

  • Liv Marina construction site, inspection photo 1, 9 August 2022
  • Liv Marina construction site, inspection photo 2, 9 August 2022
  • Liv Marina construction site, inspection photo 3, 9 August 2022
  • Liv Marina construction site, inspection photo 4, 9 August 2022

2 February 2022

6.3%

  • Liv Marina construction site, inspection photo 1, 2 February 2022
  • Liv Marina construction site, inspection photo 2, 2 February 2022
  • Liv Marina construction site, inspection photo 3, 2 February 2022
  • Liv Marina construction site, inspection photo 4, 2 February 2022

All 58 site photos, by inspection date

Context

Dubai Marina has 13 projects under construction, 46% built on average.

Own a unit in Liv Marina?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Liv Marina handover date?
Construction of Liv Marina is recorded as complete, with a registered completion date of May 2025. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Liv Marina?
Liv Marina was 100% built at the site inspection on 17 April 2025. The site has been inspected 8 times since February 2022. The Land Department took 58 site photos at its inspections.
Is Liv Marina delayed?
The register lists construction as complete.
Who is building Liv Marina?
The registered developer is L I V Real Estate Development.
Which bank holds the escrow account for Liv Marina?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.