Veona By Gutti construction progress

The registered completion date for Veona By Gutti in Dubai Land Residence Complex is December 2027. At the last site inspection, in October 2026, it was 22% built. The developer is Gutti Real Estate Development.

22%

Built, at the site inspection of 14 October 2026

Running behind its date

Registered completion date
December 2027
Finish at recent pace
July 2029
Construction started
November 2025
First registered
September 2025
Developer
Gutti Real Estate Development
Units
90
Escrow bank
Mashreq Bank
Name in Arabic
فيونا من غوطي
Project number
4001
Site inspections
4

Schedule

Between February 2026 and October 2026 the site added about 2.4 points a month. At that rate it would finish around July 2029, more than three months after its registered date of December 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 October 2026

22%+11 pts

  • Veona By Gutti construction site, inspection photo 1, 14 October 2026
  • Veona By Gutti construction site, inspection photo 2, 14 October 2026
  • Veona By Gutti construction site, inspection photo 3, 14 October 2026
  • Veona By Gutti construction site, inspection photo 4, 14 October 2026

18 June 2026

11%+8.9 pts

  • Veona By Gutti construction site, inspection photo 1, 18 June 2026
  • Veona By Gutti construction site, inspection photo 2, 18 June 2026
  • Veona By Gutti construction site, inspection photo 3, 18 June 2026
  • Veona By Gutti construction site, inspection photo 4, 18 June 2026

9 February 2026

2.1%+2.1 pts

  • Veona By Gutti construction site, inspection photo 1, 9 February 2026
  • Veona By Gutti construction site, inspection photo 2, 9 February 2026
  • Veona By Gutti construction site, inspection photo 3, 9 February 2026
  • Veona By Gutti construction site, inspection photo 4, 9 February 2026

11 August 2025

0%

  • Veona By Gutti construction site, inspection photo 1, 11 August 2025
  • Veona By Gutti construction site, inspection photo 2, 11 August 2025

All 17 site photos, by inspection date

Context

Dubai Land Residence Complex has 63 projects under construction, 28% built on average.

Own a unit in Veona By Gutti?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Veona By Gutti handover date?
The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Veona By Gutti?
Veona By Gutti was 22% built at the site inspection on 14 October 2026. The site has been inspected 4 times since August 2025. The Land Department took 17 site photos at its inspections.
Is Veona By Gutti delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Veona By Gutti?
The registered developer is Gutti Real Estate Development.
Which bank holds the escrow account for Veona By Gutti?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.