Veona By Gutti construction progress

Veona By Gutti in Dubai Land Residence Complex is 11% built at the Land Department inspection of June 2026. Developer Gutti Real Estate Development. Completion registered for December 2027.

11%

Built, at the Land Department site inspection of 18 June 2026

Running behind its date

Completion date (Land Department)
December 2027
Finish at recent pace
April 2033
Construction started
November 2025
Registered with the Land Department
September 2025
Developer
Gutti Real Estate Development
Units
90
Escrow bank
Mashreq Bank
Name in Arabic
فيونا من غوطي
Land Department project number
4001
Land Department site inspections
3

Schedule

Between August 2025 and June 2026 the site added about 1.1 points a month. At that rate it would finish around April 2033, more than three months after the December 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

18 June 2026

11%+8.9 pts

  • Veona By Gutti construction site, Land Department inspection photo 1, 18 June 2026
  • Veona By Gutti construction site, Land Department inspection photo 2, 18 June 2026
  • Veona By Gutti construction site, Land Department inspection photo 3, 18 June 2026
  • Veona By Gutti construction site, Land Department inspection photo 4, 18 June 2026

9 February 2026

2.1%+2.1 pts

  • Veona By Gutti construction site, Land Department inspection photo 1, 9 February 2026
  • Veona By Gutti construction site, Land Department inspection photo 2, 9 February 2026
  • Veona By Gutti construction site, Land Department inspection photo 3, 9 February 2026
  • Veona By Gutti construction site, Land Department inspection photo 4, 9 February 2026

11 August 2025

0%

  • Veona By Gutti construction site, Land Department inspection photo 1, 11 August 2025
  • Veona By Gutti construction site, Land Department inspection photo 2, 11 August 2025

All 11 site photos, by inspection date

Context

Dubai Land Residence Complex has 65 projects under construction, 24% built on average.

Own a unit in Veona By Gutti?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Veona By Gutti be completed?
The completion date registered with the Dubai Land Department is December 2027. At the pace of its recent inspections the site would reach 100% around April 2033. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Veona By Gutti is built?
11%, measured at the Land Department site inspection on 18 June 2026. The Land Department engineers have inspected the site 3 times since August 2025.
Is Veona By Gutti delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
Who is building Veona By Gutti?
The registered developer is Gutti Real Estate Development.
Which bank holds the escrow account for Veona By Gutti?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.