Veona By Gutti construction photos

11 photos taken by Dubai Land Department engineers at 3 site inspections, newest first. The percentage is how much of Veona By Gutti was built on the day of each visit.

18 June 202611% built

9 February 20262.1% built

11 August 20250% built

Back to Veona By Gutti construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.