The Boulevard By Prestige One construction progress
The Boulevard By Prestige One in Dubai Land Residence Complex is 11% built at the Land Department inspection of September 2026. Developer Prestige The Boulevard Real Estate Development. Completion registered for November 2027.
11%
Built, at the Land Department site inspection of 23 September 2026
Running behind its date
- Completion date (Land Department)
- November 2027
- Finish at recent pace
- October 2034
- Construction started
- July 2025
- Registered with the Land Department
- January 2025
- Developer
- Prestige The Boulevard Real Estate Development
- Community
- Dubai Land Residence Complex
- Units
- 387
- Escrow bank
- Emirates NBD
- Name in Arabic
- ذا بوليفارد من برستيج وان
- Land Department project number
- 3428
- Land Department site inspections
- 4
Schedule
Between November 2025 and September 2026 the site added about 0.9 points a month. At that rate it would finish around October 2034, more than three months after the November 2027 date registered with the Land Department.
Site inspections
23 September 2026
11%+5.8 pts
23 June 2026
4.8%+3.8 pts
14 November 2025
1.1%+1.1 pts
4 December 2024
0%
Context
Dubai Land Residence Complex has 65 projects under construction, 24% built on average.
Own a unit in The Boulevard By Prestige One?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will The Boulevard By Prestige One be completed?
- The completion date registered with the Dubai Land Department is November 2027. At the pace of its recent inspections the site would reach 100% around October 2034. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of The Boulevard By Prestige One is built?
- 11%, measured at the Land Department site inspection on 23 September 2026. The Land Department engineers have inspected the site 4 times since December 2024.
- Is The Boulevard By Prestige One delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
- Who is building The Boulevard By Prestige One?
- The registered developer is Prestige The Boulevard Real Estate Development.
- Which bank holds the escrow account for The Boulevard By Prestige One?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Ag CentralNearby in Dubai Land Residence Complex. 59%, Due October 2026.
- Ag SquareNearby in Dubai Land Residence Complex. 69%.
- Time 2Nearby in Dubai Land Residence Complex. 87%, Due June 2026, passed.
- Ag 7evenNearby in Dubai Land Residence Complex. 94%, Due March 2027.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.





.jpeg&w=3840&q=75)