The Boulevard By Prestige One construction progress

The Boulevard By Prestige One in Dubai Land Residence Complex is 11% built at the Land Department inspection of September 2026. Developer Prestige The Boulevard Real Estate Development. Completion registered for November 2027.

11%

Built, at the Land Department site inspection of 23 September 2026

Running behind its date

Completion date (Land Department)
November 2027
Finish at recent pace
October 2034
Construction started
July 2025
Registered with the Land Department
January 2025
Developer
Prestige The Boulevard Real Estate Development
Units
387
Escrow bank
Emirates NBD
Name in Arabic
ذا بوليفارد من برستيج وان
Land Department project number
3428
Land Department site inspections
4

Schedule

Between November 2025 and September 2026 the site added about 0.9 points a month. At that rate it would finish around October 2034, more than three months after the November 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

23 September 2026

11%+5.8 pts

  • The Boulevard By Prestige One construction site, Land Department inspection photo 1, 23 September 2026
  • The Boulevard By Prestige One construction site, Land Department inspection photo 2, 23 September 2026
  • The Boulevard By Prestige One construction site, Land Department inspection photo 3, 23 September 2026
  • The Boulevard By Prestige One construction site, Land Department inspection photo 4, 23 September 2026

23 June 2026

4.8%+3.8 pts

  • The Boulevard By Prestige One construction site, Land Department inspection photo 1, 23 June 2026
  • The Boulevard By Prestige One construction site, Land Department inspection photo 2, 23 June 2026
  • The Boulevard By Prestige One construction site, Land Department inspection photo 3, 23 June 2026
  • The Boulevard By Prestige One construction site, Land Department inspection photo 4, 23 June 2026

14 November 2025

1.1%+1.1 pts

  • The Boulevard By Prestige One construction site, Land Department inspection photo 1, 14 November 2025
  • The Boulevard By Prestige One construction site, Land Department inspection photo 2, 14 November 2025
  • The Boulevard By Prestige One construction site, Land Department inspection photo 3, 14 November 2025

4 December 2024

0%

  • The Boulevard By Prestige One construction site, Land Department inspection photo 1, 4 December 2024
  • The Boulevard By Prestige One construction site, Land Department inspection photo 2, 4 December 2024

All 13 site photos, by inspection date

Context

Dubai Land Residence Complex has 65 projects under construction, 24% built on average.

Own a unit in The Boulevard By Prestige One?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will The Boulevard By Prestige One be completed?
The completion date registered with the Dubai Land Department is November 2027. At the pace of its recent inspections the site would reach 100% around October 2034. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of The Boulevard By Prestige One is built?
11%, measured at the Land Department site inspection on 23 September 2026. The Land Department engineers have inspected the site 4 times since December 2024.
Is The Boulevard By Prestige One delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
Who is building The Boulevard By Prestige One?
The registered developer is Prestige The Boulevard Real Estate Development.
Which bank holds the escrow account for The Boulevard By Prestige One?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.