Park Gate construction photos
78 photos from 9 site inspections, newest first. The percentage is how much of Park Gate was built on the day of each visit.
11 August 202690% built
3 June 202683% built
12 February 202672% built
5 January 202666% built
19 September 202550% built
18 April 202521% built
18 November 20247.2% built
6 June 20241.1% built
14 November 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.