Skip to content

Golf Place construction progress

The register lists Golf Place in Dubai Hills - Golf Place as complete, with a registered completion date of February 2023. Its last site inspection on record was in April 2023. The developer is Dubai Hills Estate.

100%

Built, at the site inspection of 3 April 2023

Construction complete

Registered completion date
February 2023
Construction started
January 2018
First registered
January 2018
Community
Dubai Hills - Golf Place
Units
158
Escrow bank
First Abu Dhabi Bank
Name in Arabic
جولف بلايس
Project number
2016
Site inspections
21

Schedule

The register lists Golf Place as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20192020202120222023
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

3 April 2023

100%+1.9 pts

  • Golf Place construction site, inspection photo 1, 3 April 2023
  • Golf Place construction site, inspection photo 2, 3 April 2023
  • Golf Place construction site, inspection photo 3, 3 April 2023
  • Golf Place construction site, inspection photo 4, 3 April 2023

7 February 2023

98%+0.7 pts

  • Golf Place construction site, inspection photo 1, 7 February 2023
  • Golf Place construction site, inspection photo 2, 7 February 2023
  • Golf Place construction site, inspection photo 3, 7 February 2023
  • Golf Place construction site, inspection photo 4, 7 February 2023

24 November 2022

97%+0.3 pts

  • Golf Place construction site, inspection photo 1, 24 November 2022
  • Golf Place construction site, inspection photo 2, 24 November 2022
  • Golf Place construction site, inspection photo 3, 24 November 2022
  • Golf Place construction site, inspection photo 4, 24 November 2022

9 November 2022

97%+0.5 pts

  • Golf Place construction site, inspection photo 1, 9 November 2022
  • Golf Place construction site, inspection photo 2, 9 November 2022
  • Golf Place construction site, inspection photo 3, 9 November 2022
  • Golf Place construction site, inspection photo 4, 9 November 2022

30 September 2022

97%+1.6 pts

  • Golf Place construction site, inspection photo 1, 30 September 2022
  • Golf Place construction site, inspection photo 2, 30 September 2022
  • Golf Place construction site, inspection photo 3, 30 September 2022
  • Golf Place construction site, inspection photo 4, 30 September 2022

15 August 2022

95%+2.0 pts

  • Golf Place construction site, inspection photo 1, 15 August 2022
  • Golf Place construction site, inspection photo 2, 15 August 2022
  • Golf Place construction site, inspection photo 3, 15 August 2022
  • Golf Place construction site, inspection photo 4, 15 August 2022

28 June 2022

93%+2.7 pts

  • Golf Place construction site, inspection photo 1, 28 June 2022
  • Golf Place construction site, inspection photo 2, 28 June 2022
  • Golf Place construction site, inspection photo 3, 28 June 2022
  • Golf Place construction site, inspection photo 4, 28 June 2022

18 May 2022

90%+0.3 pts

  • Golf Place construction site, inspection photo 1, 18 May 2022
  • Golf Place construction site, inspection photo 2, 18 May 2022
  • Golf Place construction site, inspection photo 3, 18 May 2022
  • Golf Place construction site, inspection photo 4, 18 May 2022

19 April 2022

90%+9.8 pts

  • Golf Place construction site, inspection photo 1, 19 April 2022
  • Golf Place construction site, inspection photo 2, 19 April 2022
  • Golf Place construction site, inspection photo 3, 19 April 2022
  • Golf Place construction site, inspection photo 4, 19 April 2022

21 November 2021

80%+5.7 pts

  • Golf Place construction site, inspection photo 1, 21 November 2021
  • Golf Place construction site, inspection photo 2, 21 November 2021
  • Golf Place construction site, inspection photo 3, 21 November 2021
  • Golf Place construction site, inspection photo 4, 21 November 2021

All 219 site photos, by inspection date

Context

Dubai Hills Estate has 18 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Golf Place?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Golf Place handover date?
Construction of Golf Place is recorded as complete, with a registered completion date of February 2023. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Golf Place?
Golf Place was 100% built at the site inspection on 3 April 2023. The site has been inspected 21 times since July 2018. The Land Department took 219 site photos at its inspections.
Is Golf Place delayed?
The register lists construction as complete.
Who is building Golf Place?
The registered developer is Dubai Hills Estate. It has 18 other projects under construction in Dubai.
Which bank holds the escrow account for Golf Place?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.