Golf Place construction photos

219 photos from 21 site inspections, newest first. The percentage is how much of Golf Place was built on the day of each visit.

3 April 2023100% built

7 February 202398% built

24 November 202297% built

9 November 202297% built

30 September 202297% built

15 August 202295% built

28 June 202293% built

18 May 202290% built

19 April 202290% built

21 November 202180% built

11 August 202175% built

20 April 202161% built

28 December 202047% built

14 September 202038% built

7 June 202030% built

12 February 202018% built

13 October 20198.9% built

10 July 20194.2% built

11 March 20193.4% built

22 November 20183.0% built

23 July 20181.6% built

Back to Golf Place construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.