Lumina construction progress
The registered completion date for Lumina in Dubai Health Care City Phase 1 is April 2028. At the last site inspection, in July 2026, it was 11% built. The developer is Yehiaco Real Estate.
11%
Built, at the site inspection of 22 July 2026
Running behind its date
- Registered completion date
- April 2028
- Finish at recent pace
- July 2032
- Construction started
- September 2024
- First registered
- May 2025
- Developer
- Yehiaco Real Estate
- Community
- Dubai Health Care City Phase 1
- Units
- 24
- Escrow bank
- Emirates NBD
- Name in Arabic
- لومينا
- Project number
- 3275
- Site inspections
- 3
Schedule
Between December 2025 and July 2026 the site added about 1.2 points a month. At that rate it would finish around July 2032, more than three months after its registered date of April 2028.
Site inspections
22 July 2026
11%+8.3 pts
30 December 2025
3.1%+3.1 pts
25 March 2025
0%
Context
Dubai Health Care City Phase 1 has 2 projects under construction, 7.2% built on average.
Own a unit in Lumina?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Lumina handover date?
- The registered completion date is April 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2032. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Lumina?
- Lumina was 11% built at the site inspection on 22 July 2026. The site has been inspected 3 times since March 2025. The Land Department took 12 site photos at its inspections.
- Is Lumina delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2028.
- Who is building Lumina?
- The registered developer is Yehiaco Real Estate.
- Which bank holds the escrow account for Lumina?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Azizi EmeraldNearby in Dubai Health Care City Phase 1. 3.0%, Due February 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)