Damac Bay construction photos
57 photos taken by Dubai Land Department engineers at 10 site inspections, newest first. The percentage is how much of Damac Bay was built on the day of each visit.
18 August 202634% built
17 April 202629% built
15 December 202525% built
15 April 202516% built
11 December 20248.8% built
5 July 20245.9% built
13 March 20244.2% built
5 December 20232.5% built
7 September 20230% built
18 January 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.

















.jpg&w=3840&q=75)








.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)











.jpg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)