The Cove construction progress

The register lists The Cove in Dubai Creek Harbour as complete, with a registered completion date of November 2021. Its last site inspection on record was in November 2021. The developer is The Lagoons Phase One.

100%

Built, at the site inspection of 17 November 2021

Construction complete

Registered completion date
November 2021
Construction started
January 2017
First registered
November 2016
Units
291
Escrow bank
Mashreq Bank
Name in Arabic
ذي كوف
Project number
1826
Site inspections
16

Schedule

The register lists The Cove as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2018201920202021
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 November 2021

100%+4.8 pts

  • The Cove construction site, inspection photo 1, 17 November 2021
  • The Cove construction site, inspection photo 2, 17 November 2021
  • The Cove construction site, inspection photo 3, 17 November 2021
  • The Cove construction site, inspection photo 4, 17 November 2021

7 September 2021

95%+1.5 pts

  • The Cove construction site, inspection photo 1, 7 September 2021
  • The Cove construction site, inspection photo 2, 7 September 2021
  • The Cove construction site, inspection photo 3, 7 September 2021
  • The Cove construction site, inspection photo 4, 7 September 2021

24 May 2021

94%+3.5 pts

  • The Cove construction site, inspection photo 1, 24 May 2021
  • The Cove construction site, inspection photo 2, 24 May 2021
  • The Cove construction site, inspection photo 3, 24 May 2021
  • The Cove construction site, inspection photo 4, 24 May 2021

7 February 2021

90%+3.9 pts

  • The Cove construction site, inspection photo 1, 7 February 2021
  • The Cove construction site, inspection photo 2, 7 February 2021
  • The Cove construction site, inspection photo 3, 7 February 2021
  • The Cove construction site, inspection photo 4, 7 February 2021

1 November 2020

86%+6.1 pts

  • The Cove construction site, inspection photo 1, 1 November 2020
  • The Cove construction site, inspection photo 2, 1 November 2020
  • The Cove construction site, inspection photo 3, 1 November 2020
  • The Cove construction site, inspection photo 4, 1 November 2020

9 July 2020

80%+9.1 pts

  • The Cove construction site, inspection photo 1, 9 July 2020
  • The Cove construction site, inspection photo 2, 9 July 2020
  • The Cove construction site, inspection photo 3, 9 July 2020
  • The Cove construction site, inspection photo 4, 9 July 2020

12 March 2020

71%+6.9 pts

  • The Cove construction site, inspection photo 1, 12 March 2020
  • The Cove construction site, inspection photo 2, 12 March 2020
  • The Cove construction site, inspection photo 3, 12 March 2020
  • The Cove construction site, inspection photo 4, 12 March 2020

22 January 2020

64%+14 pts

  • The Cove construction site, inspection photo 1, 22 January 2020
  • The Cove construction site, inspection photo 2, 22 January 2020
  • The Cove construction site, inspection photo 3, 22 January 2020
  • The Cove construction site, inspection photo 4, 22 January 2020

7 October 2019

50%+10 pts

  • The Cove construction site, inspection photo 1, 7 October 2019
  • The Cove construction site, inspection photo 2, 7 October 2019
  • The Cove construction site, inspection photo 3, 7 October 2019
  • The Cove construction site, inspection photo 4, 7 October 2019

1 July 2019

40%+12 pts

  • The Cove construction site, inspection photo 1, 1 July 2019
  • The Cove construction site, inspection photo 2, 1 July 2019
  • The Cove construction site, inspection photo 3, 1 July 2019
  • The Cove construction site, inspection photo 4, 1 July 2019

All 155 site photos, by inspection date

Context

Dubai Creek Harbour has 14 projects under construction, 53% built on average.

The Lagoons Phase One has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Cove?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the The Cove handover date?
Construction of The Cove is recorded as complete, with a registered completion date of November 2021. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on The Cove?
The Cove was 100% built at the site inspection on 17 November 2021. The site has been inspected 16 times since July 2017. The Land Department took 155 site photos at its inspections.
Is The Cove delayed?
The register lists construction as complete.
Who is building The Cove?
The registered developer is The Lagoons Phase One. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for The Cove?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.