Silva construction progress

The registered completion date for Silva in Dubai Creek Harbour is September 2029. At the last site inspection, in July 2026, it was 10% built. The developer is Dubai Creek Harbour.

10%

Built, at the site inspection of 19 July 2026

Running behind its date

Registered completion date
September 2029
Finish at recent pace
May 2037
Construction started
August 2025
First registered
May 2025
Units
437
Escrow bank
Emirates Islamic Bank
Name in Arabic
سيلفا
Project number
3710
Site inspections
4

Schedule

Between December 2025 and July 2026 the site added about 0.7 points a month. At that rate it would finish around May 2037, more than three months after its registered date of September 2029.

0%25%50%75%100%2026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

19 July 2026

10%+3.9 pts

  • Silva construction site, inspection photo 1, 19 July 2026
  • Silva construction site, inspection photo 2, 19 July 2026
  • Silva construction site, inspection photo 3, 19 July 2026
  • Silva construction site, inspection photo 4, 19 July 2026

27 March 2026

6.3%+1.0 pts

  • Silva construction site, inspection photo 1, 27 March 2026
  • Silva construction site, inspection photo 2, 27 March 2026
  • Silva construction site, inspection photo 3, 27 March 2026

17 December 2025

5.3%+5.3 pts

  • Silva construction site, inspection photo 1, 17 December 2025
  • Silva construction site, inspection photo 2, 17 December 2025
  • Silva construction site, inspection photo 3, 17 December 2025
  • Silva construction site, inspection photo 4, 17 December 2025

23 April 2025

0%

  • Silva construction site, inspection photo 1, 23 April 2025
  • Silva construction site, inspection photo 2, 23 April 2025

All 14 site photos, by inspection date

Context

Dubai Creek Harbour has 14 projects under construction, 53% built on average.

Dubai Creek Harbour has 15 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Silva?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Silva handover date?
The registered completion date is September 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2037. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Silva?
Silva was 10% built at the site inspection on 19 July 2026. The site has been inspected 4 times since April 2025. The Land Department took 14 site photos at its inspections.
Is Silva delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2029.
Who is building Silva?
The registered developer is Dubai Creek Harbour. It has 14 other projects under construction in Dubai.
Which bank holds the escrow account for Silva?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.