Silva construction progress

Silva in Dubai Creek Harbour is 10% built at the Land Department inspection of July 2026. Developer Dubai Creek Harbour. Completion registered for September 2029.

10%

Built, at the Land Department site inspection of 19 July 2026

Running behind its date

Completion date (Land Department)
September 2029
Finish at recent pace
May 2037
Construction started
August 2025
Registered with the Land Department
May 2025
Units
437
Escrow bank
Emirates Islamic Bank
Name in Arabic
سيلفا
Land Department project number
3710
Land Department site inspections
4

Schedule

Between December 2025 and July 2026 the site added about 0.7 points a month. At that rate it would finish around May 2037, more than three months after the September 2029 date registered with the Land Department.

0%25%50%75%100%2026202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

19 July 2026

10%+3.9 pts

  • Silva construction site, Land Department inspection photo 1, 19 July 2026
  • Silva construction site, Land Department inspection photo 2, 19 July 2026
  • Silva construction site, Land Department inspection photo 3, 19 July 2026
  • Silva construction site, Land Department inspection photo 4, 19 July 2026

27 March 2026

6.3%+1.0 pts

  • Silva construction site, Land Department inspection photo 1, 27 March 2026
  • Silva construction site, Land Department inspection photo 2, 27 March 2026
  • Silva construction site, Land Department inspection photo 3, 27 March 2026

17 December 2025

5.3%+5.3 pts

  • Silva construction site, Land Department inspection photo 1, 17 December 2025
  • Silva construction site, Land Department inspection photo 2, 17 December 2025
  • Silva construction site, Land Department inspection photo 3, 17 December 2025
  • Silva construction site, Land Department inspection photo 4, 17 December 2025

23 April 2025

0%

  • Silva construction site, Land Department inspection photo 1, 23 April 2025
  • Silva construction site, Land Department inspection photo 2, 23 April 2025

All 14 site photos, by inspection date

Context

Dubai Creek Harbour has 14 projects under construction, 41% built on average.

Dubai Creek Harbour has 15 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Silva?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Silva be completed?
The completion date registered with the Dubai Land Department is September 2029. At the pace of its recent inspections the site would reach 100% around May 2037. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Silva is built?
10%, measured at the Land Department site inspection on 19 July 2026. The Land Department engineers have inspected the site 4 times since April 2025.
Is Silva delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2029.
Who is building Silva?
The registered developer is Dubai Creek Harbour. It has 14 other projects under construction in Dubai.
Which bank holds the escrow account for Silva?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.