Montiva construction progress

The registered completion date for Montiva in Dubai Creek Harbour is September 2029. At the last site inspection, in November 2026, it was 13% built. The developer is Dubai Creek Harbour.

13%

Built, at the site inspection of 23 November 2026

Running behind its date

Registered completion date
September 2029
Finish at recent pace
July 2034
Construction started
October 2025
First registered
May 2025
Units
475
Escrow bank
Emirates Islamic Bank
Name in Arabic
مونتيفا
Project number
3744
Site inspections
4

Schedule

Between January 2026 and November 2026 the site added about 0.9 points a month. At that rate it would finish around July 2034, more than three months after its registered date of September 2029.

0%25%50%75%100%2026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

23 November 2026

13%+7.2 pts

  • Montiva construction site, inspection photo 1, 23 November 2026
  • Montiva construction site, inspection photo 2, 23 November 2026
  • Montiva construction site, inspection photo 3, 23 November 2026
  • Montiva construction site, inspection photo 4, 23 November 2026

22 April 2026

5.8%+2.4 pts

  • Montiva construction site, inspection photo 1, 22 April 2026
  • Montiva construction site, inspection photo 2, 22 April 2026

20 January 2026

3.5%+3.5 pts

  • Montiva construction site, inspection photo 1, 20 January 2026
  • Montiva construction site, inspection photo 2, 20 January 2026
  • Montiva construction site, inspection photo 3, 20 January 2026
  • Montiva construction site, inspection photo 4, 20 January 2026

13 May 2025

0%

  • Montiva construction site, inspection photo 1, 13 May 2025
  • Montiva construction site, inspection photo 2, 13 May 2025

All 13 site photos, by inspection date

Context

Dubai Creek Harbour has 14 projects under construction, 53% built on average.

Dubai Creek Harbour has 15 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Montiva?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Montiva handover date?
The registered completion date is September 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2034. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Montiva?
Montiva was 13% built at the site inspection on 23 November 2026. The site has been inspected 4 times since May 2025. The Land Department took 13 site photos at its inspections.
Is Montiva delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2029.
Who is building Montiva?
The registered developer is Dubai Creek Harbour. It has 14 other projects under construction in Dubai.
Which bank holds the escrow account for Montiva?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.